This page was last updated on April 30, 2024

Status- April 2024

Emergency permit application materials:

Status - January 2024

The Department made an application to the Division of Dam Safety seeking an approval for a waiver for a permit under 25 Pa Code, Chapter 105.12 (a) (16) to allow for the construction of the Primrose Creek restorative channel and floodplain to eliminate the potential artificial dam structure at the Eastern perimeter of the now water filled quarry pit at the former New Hope Crushed Stone Co. Quarry.

The application and associated appendices containing the design of the channel, the discussion of the final elevation of the outlet from the quarry and the hydrologic and hydraulic study of the effects to downstream Primrose Creek may be found here.

 

Status – Fall 2018

In accord with the January 29, 2016, letter to NHCS by the Pennsylvania Department of Environmental Protection (DEP) providing requirements to complete reclamation of the quarry by March 2019, DEP staff continues to conduct inspections and adherence to this timetable. As part of this process, NHCS will be conducting aerial surveys of the quarry to be able to show progress in reclaiming the areas of the rim of the quarry which they are responsible for (all but the southern end). These will be done the end of September and December 2018 and followed by status reports posted to this page after about six weeks.

One of the components of the final reclamation phase includes blasting along the east wall of the quarry beginning sometime this fall. DEP will provide information to Solebury Township, Solebury School, the Primrose Creek Watershed Association, and this web page on the specific timing on when this will begin. As with all blasting, DEP will be monitoring for compliance.

Another condition of winding down the operation of the quarry is the restoration of Primrose Creek. Progress to date can be seen in the posted status reports. With the wet weather that has occurred this year, work on the creek has been delayed. The next project status report to coincide with the results of the end of September quarry aerial survey will include details on the work required to complete the stream restoration and the degree to which they are finished. This includes the inlet structure, placement of stone in the stream bed, and the installation of cribbing and vegetation along the banks. Future updates will include completion of the outlet structure.

After March 2019, DEP will continue to inspect and monitor the quarry to insure the reclamation is stable in terms of possible erosion issues and vegetation taking hold for a five year period.

The DEP will continue to be involved with the Solebury Communications Group through completion of all reclamation and stream restoration work. This group consists of representatives from Solebury Township, Solebury School, and the Primrose Creek Watershed Association, has been meeting with staff from DEP since March 2016 to discuss the status of the quarry and address questions and concerns.

Related Documents

July 9, 2010 - Hydrogeologic Investigation Report Addendum (PDF)
September 11, 2014 DEP technical deficiency letter to NHCS (PDF)
February 17, 2015 Solebury School Attorney response to DEP on NHCS permit issues (PDF)
March 9, 2015 EarthRes request for Army jurisdictional determination (PDF)
March 24, 2015 EarthRes response to DEP Feb. 24, 2015 letter (PDF)
April 7, 2015 Solebury School letter to DEP (PDF)
April 10, 2015 Solebury School Attorney letter to DEP re: NPDES renewal (PDF)
June 2, 2015 DEP response to Solebury School Feb. 17, 2015 letter (PDF)
June 29, 2015 Solebury School Attorney Response to DEP June 2, 2015 Letter (PDF)
July 10, 2015 DEP letter to NHCS deficient reclamation plan (PDF)
July 29, 2015 Dept. of Army letter to NHCS (PDF)
August 7, 2015 EarthRes Response DEP July 10, 2015 Letter (PDF)
August 11, 2015 DEP Response to EarthRes (PDF)
August 26, 2015 EarthRes Response to DEP August 11, 2015 Letter (PDF)
October 22, 2015 letter to NHCS from reclamation consultants (PDF)
October 28, 2015 NHCS letter to DEP, CO extension (PDF)
October 28, 2015 EarthRes CO extension request to DEP (PDF)
October 29, 2015 NHCS appeal to DEP CO (PDF)
November 4, 2015 PCWA letter to DEP, CO extension (PDF)
November 6, 2015 Solebury School letter to DEP, CO extension (PDF)
November 19, 2015 Solebury Twp. letter to DEP, CO extension (PDF)
November 30, 2015 EarthRes response to DEP, CO (PDF)
December 2, 2015 NHCS appeal of DEP (PDF)
December 18, 2015 PCWA letter to DEP (PDF)
January 14, 2016 DEP to NHCS, re: NOV (PDF)
January 29, 2016 DEP Letter to NHCS Modifying Reclamation Plan (PDF)
January 29, 2016 Consent Assessment to NHCS (PDF)
February 24, 2016 Info Request to NHCS (PDF)
February 29, 2016 NHCS notice of appeal to DEP (PDF)
March 9, 2016 Info Request to NHCS (PDF)
March 28, 2016 Pit Sump Relocation (PDF)
May 16, 2016 Bond Deficiency Letter to NHCS (PDF)
June 10, 2016 EarthRes Response to DEP May 13, 2016 Letter (PDF)
June 13, 2016 DEP Bond Request to NHCS (PDF)
July 13, 2016 DEP PILB letter to NHCS (PDF)
August 9, 2016 DEP to NHCS re Increased Payment in Lieu of Bond (PDF)
August 10, 2016 DEP to NHCS re GP104 (PDF)
August 31, 2016 DEP to NHCS PILB Approval and Full Cost Bonding (PDF)
September 23, 2016 EarthRes Corrective Action Plan to DEP (PDF)
October 21, 2016 DEP to NHCS Corrective Action Plan Deficiency (PDF)
March 13, 2017 NHCS to DEP re Temp Relief Reclamation and Restoration inc copies of MSHA Citations (PDF)
April 5, 2017 DEP to NHCS re Reclamation and Restoration Temp Relief (PDF)
April 13, 2017 DEP to NHCS Updated Corrected Action Plan Approval (PDF)
May 23, 2017 DEP to NHCS re Upcoming Corrective Action Plan July 1 Completion Date (PDF)
June 16, 2017 DEP to NHCS Corrective Action Plan reporting and inclement weather issues (PDF)
June 16, 2017 NHCS to DEP re Relief From Reclamation and Restoration Timeline (PDF)
June 27, 2017 DEP to NHCS re Relief From Reclamation and Restoration Timeline Decision (PDF)
August 29, 2017 DEP to NHCS Civil Penalty Notification (PDF)
December 4, 2017 DEP to NHCS re 4th Quarter Report Requirements (PDF)
Feb 23, 2018 NHCS to DEP Dec 4, 2017 Letter (PDF)
Feb 27, 2018 DEP to NHCS Feb 23, 2018 Letter Additional Info Needed (PDF)
April 10, 2018 NHCS response to DEP February 27, 2018 letter (PDF)
April 26, 2018 DEP to NHCS re NHCS April 10, 2018, response to DEP February 27, 2018 Letter (PDF)
April 30, 2018 NHCS to DEP Transformer Relocation Initial Plan and Costs (PDF)
May 18, 2018 EarthRes to DEP Transformer Relocation Plan and Revised Reclamation Map Update (PDF)
May 18, 2018 EarthRes NHCS Reclamation Map with Updated Timetable (PDF)
May 25 2018 EarthRes to DEP Updated Module 14 and Additional Information (PDF)
July 12, 2018 DEP to NHCS Reply to April 10, 2018, Additional Information Submission (PDF)
July 23, 2018 DEP to NHCS re Clarification of DEP July 12, 2018 letter to NHCS (PDF)
August 13, 2018 Response to Comment #3 of the Department’s July 12 and 23, 2018 Letters (PDF)
November 1, 2018 NHCS Furlong Fault Blasting Review (PDF)
November 1, 2018 NCSC Furlong Fault Blasting Approval (PDF)
October 3, 2018 DEP to NHCS Time Extension Letter (PDF)
September 04, 2018 Solebury Letter to Duke (PDF)

Calendar Year 2014 (PDF)
Calendar Year 2015 (Partial) (PDF)
September 11, 2015 Explosives Inspection (PDF)
October 1, 2015 (PDF)
November 2, 2015 (PDF)
December 10, 2015 Explosives Inspection (PDF)
January 29, 2016 (PDF)
Feb 24 to April 1, 2016 (PDF)
April 7, 2016 (PDF)
April 15, 2016 Floating Pump Picture (Jpg)
April 15, 2016 (PDF)
April 22 and 27, 2016, with Pictures (PDF)
May 2, 2016 (PDF)
May 2, 2016 Floating Pump Picture (Jpg)
May 12, 2016 (PDF)
May 19, 2016 (PDF)
May 27, 2016 (PDF)
June 2, 2016 (DOCX)
June 9, 2016 (PDF)
June 23, 2016 (PDF)
June 29, 2016 (PDF)
July 7, 2016 (DOCX)
July 14, 2016 (PDF)
July 21, 2016 (PDF)
July 29, 2016 (PDF)
August 5, 2016 (PDF)
August 10, 2016 (PDF)
August 18, 2016 (PDF)
August 18, 2016 (PDF)
August 26, 2016 (PDF)
August 26, 2016 and Compliance Order (PDF)
September 1, 2016 (PDF)
September 9, 2016 (PDF)
September 12, 2016 Notice of Proposed Assessment (PDF)
September 13, 2016 (PDF)
September 23, 2016 (PDF)
September 30, 2016 (PDF)
October 2016 Reports - 4 Total (PDF)
November 16, 2016 (PDF)
December 7, 2016 NHCS Executed Consent Assessment of Civil Penalty (PDF)
December 2, 2016 (PDF)
December 21, 2016 (PDF)
January 6, 2017 (PDF)
January 13, 2017 (PDF)
January 27, 2017 (PDF)
February 3, 2017 (PDF)
February 16, 2017 (PDF)
March 7, 2017 (PDF)
March 16, 2017 (PDF)
April 18, 2017 (PDF)
May 2, 2017 (PDF)
June 26, 2017 (PDF)
July 10, 2017 (PDF)
July 10, 2017 (PDF)
July 14, 2017 (PDF)
August 7, 2017 (PDF)
August 10, 2017 Lifting of July 10, 2017 Compliance Order (PDF)
September 29, 2017 (PDF)
November 29, 2017 (PDF)
March 13, 2018 (PDF)
May 11, 2018 (PDF)
June 7, 2018 Blaster Inspection and May 30, 2018 Blast Plan (PDF)
August 16, 2018 (PDF)
October 5, 2018 (PDF)
October 24, 2018 (PDF)
April 16, 2019 Inspection Report and Compliance Order (PDF)