The PA Pipeline Project (PPP)/Mariner East II is an expansion of the existing Sunoco Mariner East pipeline system. Sunoco recently upgraded its existing Mariner East I pipeline to transport natural gas liquids from Ohio and the Pittsburgh area to its Marcus Hook Facility in Delaware County. More than 80% of the PPP will follow the same pipeline corridor as Mariner East I. The pipeline will traverse 17 counties in the southern tier of Pennsylvania.
Below is information on DEP's review and approval of the permit applications and other useful project information. The material is presented here to enable the public to readily review the application material, noted technical deficiencies and the company's responses to the technical deficiencies. The other material on this web page represents other documents associated with this project that the Department has received.
Additional documents, such as additional correspondence and emails between the DEP and the Applicant, may be in DEP files maintained at that regional office in which a given portion of the project is located. Persons wishing to review the entire file for this application should schedule a file review with the appropriate regional office (i.e. Southwest, South-Central or Southeast).
PPP/Mariner East II Project Overview Information
This information sheet provides a summary of the project and current status.
Consent Assessment of Civil Penalty (CACP)
On July 6, 2023, Sunoco Pipeline, L.P. entered into two recent CACPs with the Department, agreeing to pay $660,000.00 to resolve civil penalty liability for the violations set out in the documents. Links to both fully executed civil penalty agreements are included below.
- Press Release
- CACP- Exton Library
- CACP -Berks, Blair, Cambria, Chester, Cumberland, Delaware, Perry, York Counties
Chapter 102, Erosion & Sediment Control Permit Renewals and Partial Notices of Termination
As noted below, during DEP’s review of the Partial Notice of Termination (NOT) forms and the Chapter 102 E&S Permit Renewal Applications, Sunoco Pipeline, L.P. has voluntarily withdrawn and submitted revised NOT forms with updated plans to accurately reflect the most current field conditions. Sunoco Pipeline, L.P. has also submitted revised permit renewal applications with updated plans to be consistent with the revised Partial NOT forms.
DEP’s review is ongoing for the Partial Notice of Termination (NOT) forms and the Chapter 102 E&S Permit Renewal Applications submitted by Sunoco Pipeline, L.P.
On June 20, 2023 and July 7, 2023, DEP received revised Partial NOT#3 forms with cover letters from Sunoco Pipeline, L.P. for the following previously issued E&S permits and corresponding counties.
- ESG0500015001 – Revised Partial NOT#3 - Counties: Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Revised Partial NOT#3 - Counties: Huntingdon, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Revised Partial NOT#3 - Counties: Delaware and Chester (PDF)
In May and June 2023, DEP issued Partial NOT#1 and Partial NOT#2 approvals to Sunoco Pipeline, L.P. for the following previously issued E&S permits and corresponding counties.
- ESG0500015001 – May 3, 2023 Partial NOT#1 Approval Letter for Counties: Washington, Allegheny, Cambria, Indiana and Westmoreland (PDF)
- ESG0500015001 – June 8, 2023 Partial NOT#2 Approval Letter for Counties: Cambria, Indiana and Westmoreland (PDF)
- ESG0300015002 - June 2, 2023 Partial NOT#1 & Partial NOT#2 Approval Letters for Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin
On September 2, 2022, DEP received revised Partial NOT#2 forms with cover letters from Sunoco Pipeline, L.P. for the following previously issued E&S permits and corresponding counties.
- ESG0500015001 – Revised Partial NOT#2 - Counties: Cambria, Indiana and Westmoreland (PDF)
- ESG0300015002 – Revised Partial NOT#2 - Counties: Huntingdon, Lancaster, Lebanon, Perry, York, Berks, Blair and Cumberland (PDF)
- ESG0100015001 – Revised Partial NOT#2 - Counties: Delaware and Chester (PDF)
On March 4, 2022 and March 21, 2022, DEP received the following revised Chapter 102, Erosion and Sediment Control Individual Permit renewal applications with cover letters and updated plans from Sunoco Pipeline, L.P.
- ESG0500015001 – Complete Renewal Application: Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Complete Renewal Application: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Complete Renewal Application: Delaware and Chester (PDF)
On March 4, 2022, DEP received revised Partial Notice of Termination (NOT) forms with cover letters from Sunoco Pipeline, L.P. for the following previously issued E&S permits and corresponding counties.
- ESG0500015001 – Revised Partial NOT - Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Revised Partial NOT - Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Revised Partial NOT - Counties: Delaware and Chester (PDF)
On March 2, 2022, DEP received withdrawal letters for the Partial Notice of Termination (NOT) forms from Sunoco Pipeline, L.P. for the following previously issued E&S permits and corresponding counties.
- ESG0500015001 – Withdrawal Letter - Counties: Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Withdrawal Letter - Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Withdrawal Letter - Counties: Delaware and Chester (PDF)
On January 26, 2022, DEP provided a clarification letter to Sunoco Pipeline, L.P. in regards to the administrative extension of Chapter 102 Erosion and Sediment Control Individual Permits consistent with Condition No. 4 of Permits ESG0500015001, ESG0300015002, and ESG0100015001 and the related minor modification that was granted on August 6, 2021.
On December 11, 2021, DEP provided notice in the Pennsylvania Bulletin that the Chapter 102, Erosion and Sediment Control Individual Permit renewals were under review for Sunoco Pipeline, L.P.'s PA Pipeline Project (PPP)/Mariner East II. DEP is accepting written comments for 45-days on the permit renewal applications. Please note that these renewal applications do not include any proposals for new work. They merely request to extend the permit term in areas where work remains or where soil stabilization is still underway.
On November 23, 2021, DEP sent the following completeness letters to Sunoco Pipeline, L.P. for its Chapter 102 permit renewal applications.
- ESG0500015001 – Counties: Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Counties: Delaware and Chester (PDF)
On November 16, 2021, DEP received Partial Notice of Termination (NOT) forms from Sunoco Pipeline, L.P. for the following counties pertaining to the issued E&S Permits.
- ESG0500015001 – Partial NOT - Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Partial NOT - Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Partial NOT - Counties: Delaware and Chester (PDF)
On November 10, 2021, DEP received updated General Information Forms (GIFs) from Sunoco Pipeline, L.P. for the permit renewals submitted on October 28, 2021.
- ESG0500015001 – GIF – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – GIF – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – GIF – Counites: Delaware and Chester (PDF)
On October 28, 2021, DEP received the following Chapter 102, Erosion and Sediment Control Individual Permit renewal applications from Sunoco Pipeline, L.P. Please note that these renewal applications do not include any proposals for new work. They merely request to extend the permit term in areas where work remains or where soil stabilization is still underway.
- ESG0500015001 – Counties: Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Counties: Delaware and Chester (PDF)
Compliance and Enforcement Information
Administrative Order
On September 11, 2020, DEP ordered Sunoco to reroute its planned pipeline route, and further assess, investigate, and restore resources impacted by Mariner East II pipeline installation activities at HDD 290 in Upper Uwchlan Township, Chester County.
- Administrative Order (PDF)
Resolution of Appeals
On August 27, 2020, DEP received a letter from Groundwater & Environmental Services, Inc., on behalf of Sunoco Pipeline, LP, for modifications and enhancements to mitigation and containment measures for HDD S3-0360-16, located in West Whiteland Township, Chester County, Pennsylvania. On August 28, 2020, DEP reviewed and approved Sunoco’s proposal and the Environmental Hearing Board signed a Stipulation for Settlement and Order for HDD S3-0360-16.
- Sunoco Pipeline, LP’s, Modification and Enhancement letter August 27, 2020 (PDF)
- DEP’s Approval letter August 28, 2020 (PDF)
- Stipulation for Settlement August 28, 2020 (PDF)
- Order August 28, 2020 (PDF)
On July 25, 2018 the Pennsylvania Department of Environmental Protection (DEP), the Clean Air Council (CAC), Mountain Watershed Association (MWA), and the Delaware Riverkeeper Network (DRN) settled their appeal of 20 permits issued to Sunoco Pipeline, LLP (Sunoco) for the Mariner East 2 pipeline project.
Consent Assessment of Civil Penalty
On August 5, 2021, DEP entered into a Consent Assessment of Civil Penalty (CACP) with Sunoco Pipeline, LP for violations related to the construction of the Mariner East 2 pipeline in four Pennsylvania counties: Blair, Cumberland, Juniata, and Lebanon. The violations took place between February and August 2020.
As part of the agreement, DEP has assessed a civil penalty of $85,666 for the violations, which Sunoco has agreed to pay to the commonwealth. A portion of the civil penalty, $1,166, will be paid to the county conservation districts to reimburse them for their costs incurred during their investigation of the inadvertent returns. The remaining penalty, $84,500, will be paid to the state’s Clean Water Fund. In addition to the penalty paid to the commonwealth and the county conservation districts, Sunoco will also pay a penalty of $12,424 to the Pennsylvania Fish and Boat Commission.
- Consent Assessment of Civil Penalty (PDF)
- Exhibit A (PDF)
On July 26, 2021, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline, LP for $41,039 for several incidents arising from Mariner East II pipeline construction in Delaware County over the course of 2018-20 including: (1) twice breaking a sewer lateral to a facility in Aston Township resulting in the unpermitted discharge of sewage, and failing to notify the Department; (2) flushing 30 gallons of drilling mud out of a drill pit in Edgmont Township, with 5 gallons going into Chester Creek; (3) discharging drilling fluids into an unnamed tributary (UNT) to Chester Creek in Edgmont Township when SPLP personnel fell asleep and failed to operate pumps; (4) discharging sediment laden water in Edgmont Township into a wetland and an UNT to Chester Creek after a rainfall event and during pipe pullback; and (5) discharging concrete-washout material from a grout truck onto a rock construction entrance in Edgmont Township.
On August 4, 2020, DEP entered into a Consent Assessment of Civil Penalty (CACP) with Sunoco Pipeline, LP for violations related to the construction of the Mariner East 2 pipeline in eight Pennsylvania counties: Berks, Blair, Cambria, Cumberland, Delaware, Lebanon, Washington, and Westmoreland. The violations took place between August 2018 and April 2019. As part of the agreement, DEP has assessed a civil penalty of $355,636 for the violations, which Sunoco has agreed to pay to the Commonwealth. A portion of the civil penalty, $5,912, will be paid to the county conservation districts to reimburse them for their costs incurred during their investigation of the inadvertent returns. The remaining penalty, $349,724, will be paid to the Clean Water Fund.
On August 21, 2019, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline, LP for violations resulting from construction activities on the Mariner East 2 pipeline project. Sunoco’s construction activities resulted in accelerated erosion and sedimentation in Cumberland County in violation of its permits and the Clean Streams Law.
On August 20, 2019, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline, LP for violations of its permits and the Clean Streams Law resulting from construction activities on the Mariner East 2 pipeline project and the Clean Streams Law. Sunoco’s construction activities resulted in unauthorized discharge of drilling fluids to surface waters associated with horizontal drilling activities, also known as inadvertent returns, in Berks, Blair, Cambria, Cumberland, Delaware, Huntingdon, Lebanon, Perry, Washington, and Westmoreland Counties.
On August 2, 2018, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline, LP for violations resulting from construction activities on the Mariner East 2 pipeline project. Sunoco's construction activities resulted in impacts to water supplies in Chester, Berks and Lebanon Counties in violation of its permits and the Clean Streams Law. In each instance, Sunoco was required to address those impacts to the satisfaction of the water supply's owner, including replacement or restoration of the impacted water supply. In Chester County, Sunoco also failed to immediately notify DEP of the adverse impacts to the private water supplies.
On April 27, 2018, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline LP for violations resulting from construction activities on the Mariner East 2 pipeline project. Sunoco's construction activities resulted in an unpermitted discharge of drilling fluids to wetlands, wild trout streams, and High-Quality Waters at a number of locations in Allegheny, Blair, Cambria, Cumberland, Dauphin, Huntingdon, Indiana, Lancaster, and Washington Counties in violation of its permits and the Clean Streams Law. In each instance, Sunoco was required to halt operations, remediate the impacts, and submit proposed modifications to its construction methodologies to DEP for approval. Sunoco was allowed to resume operations only after DEP reviewed and approved Sunoco's proposed modifications. This penalty is in addition to the $12.6 million penalty levied against the company in February and covers separate violations.
On December 21, 2017, DEP entered into a Consent Assessment of Civil Penalty with Sunoco Pipeline, LP for violations resulting from construction activities on the Mariner East 2 pipeline project. Sunoco's construction activities resulted in accelerated erosion and sedimentation at three sites in Lebanon County in violation of its permits and the Clean Streams Law. In each instance, Sunoco was required to install appropriate measures to effectively minimize the erosion and sedimentation issues at those sites.
Resolution of Petition for Supersedas
On April 16, 2018, the Pennsylvania Department of Environmental Protection reached an agreement with the Clean Air Council, Delaware Riverkeeper Network, and the Mountain Watershed Association, Inc. and Sunoco to resolve a petition for supersedeas filed before the Environmental Hearing Board.
That agreement can be viewed here
Below are the following Exhibits:
- Exhibit 1 - The April 2018 Inadvertent Return (IR) Assessment, Preparedness, Prevention and Contingency (PPC) Plan
- Exhibit 2 - A red line comparison of the February 6, 2018 version of the IR PPC Plan to the April 2018 HDD IR Plan
- Exhibit 3 - A red line comparison of the August 8, 2017 version of the IR PPC Plan to the April 2018 HDD IR Plan
Statement of Settlement of Suspension of Construction Activities
On February 8, 2018, DEP and Sunoco reached an agreement to lift the January 3, 2018 order suspending permits for the Mariner East 2 pipeline project. The Consent Order and Agreement includes a civil penalty of $12.6 million and resolves violations outlined in the January 3 order, as well as others discovered in the course of DEP's review. The COA and supporting documents is below, along with a breakdown of Sunoco's required actions under the January 3 order.
- Summary of Actions and Outcomes Required of DEP's Administrative Order (PDF)
- HDD Inadvertent Return Assessment, Preparedness, Prevention and Contingency Plan (PDF)
- Consent Order and Agreement (PDF)
- January 3, 2018 Order Suspending Construction Activities (PDF)
Statement on Settlement of Suspension of Drilling:
On August 9, 2017, the Pennsylvania Department of Environmental Protection reached an agreement with the Clean Air Council, Delaware Riverkeeper Network, and the Mountain Watershed Association, Inc. and Sunoco to resolve the temporary suspension of horizontal directional drilling (HDD) activity associated with construction of the ME2 pipeline being built by Sunoco, LP.
That agreement can be viewed here (PDF).
As part of the agreement reflected in the Environmental Hearing Board Stipulated Order dated August 9, 2017, Sunoco made revisions to some of the plans associated with the project, which are provided below:
- Void Mitigation Plan for Karst Terrain and Underground Mining w/ Appendices (PDF)
- HDD Inadvertent Return Assessment, Preparedness, Prevention and Contingency Plan (PDF)
- HDD Inadvertent Return Assessment, Preparedness, Prevention and Contingency Plan - Appendix C – County Attachments
- Water Supply Assessment, Preparedness, Prevention and Contingency Plan w/ Appendices (PDF)
Under the agreement, Sunoco will notify all landowners and water supply owners within 450 feet of future HDDs and provide additional opportunities for water testing for those owners. Sunoco will also reevaluate at least 63 areas where HDD activity will take place. The reevaluations will include site-specific geologic data for each location. The reevaluation reports will be posted to this webpage as they are received.
HDD Reevaluation Reports
As part of the August 9, 2017 Environmental Hearing Board Stipulated Order, Sunoco is to provide DEP for review supplemental HDD Analysis. The HDD Reevaluation Table represents the supplemental information that DEP has received to date.
Public comments can be submitted within 14 calendar days from the date each HDD study has been posted on the table by sending an email to EP-Pipelines.
To view details of each HDD study and public comments, visit the HDD Reevaluation Table. Each public comment is listed with the identifying Commentator ID number at the end of the comment.
Consent Order and Agreements:
- June 27, 2017 Middlesex Township, Cumberland County (PDF)
- July 24, 2017 Shoen Road Drill, West Whiteland Township and Uwchlan Township, Chester County (PDF)
- DEP Response Chester County (PDF)
- December 15, 2017 Loyalhanna Lake Recreation Area, Westmoreland County (PDF)
- January 3, 2020 Raystown Lake, Huntingdon County (PDF)
- February 12, 2021 Snitz Creek, West Cornwall Township, Lebanon County (PDF)
- December 6, 2021 Upper Uwchlan Township, Chester County, joint with DCNR (PDF)
Inadvertent Returns:
The following spreadsheets detail the inadvertent returns and the status of the incident for construction related to the Mariner East 2 pipeline. This information will be updated regularly.
- Sunoco Mariner East II - Pipeline Construction Inadvertent Returns - Waters of the Commonwealth Revised on April 23, 2021 (PDF)
- Sunoco Mariner East II – Pipeline Construction Inadvertent Returns – Uplands Revised on August 20, 2020 (PDF)
Accordion
- May 9, 2017 Delaware County (PDF)
- May 17, 2017 Cumberland County (PDF)
- June 5, 2017 Cumberland County (PDF)
- July 20, 2017 Delaware County (PDF)
- July 28, 2017 Allegheny County (PDF)
- July 28, 2017 Indiana County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Washington County (PDF)
- July 28, 2017 Washington County (PDF)
- August 16, 2017 Lebanon County (PDF)
- August 30, 2017 Dauphin County (PDF)
- September 8, 2017 Chester County (PDF)
- September 12, 2017 Delaware County (PDF)
- October 26, 2017 Blair County (PDF)
- October 26, 2017 Blair County (PDF)
- October 26, 2017 Dauphin County (PDF)
- October 26, 2017 Cumberland County (PDF)
- October 26, 2017 Huntingdon County (PDF)
- October 27, 2017 Lebanon County (PDF)
- October 31, 2017 Lebanon County (PDF)
- November 3, 2017 Chester County (PDF)
- November 3, 2017 Delaware County (PDF)
- November 14, 2017 Dauphin County (PDF)
- November 16, 2017 Berks County (PDF)
- November 16, 2017 Chester County (PDF)
- November 21, 2017 Berks County (PDF)
- November 22, 2017 Blair County (PDF)
- November 27, 2017 Chester County (PDF)
- December 21, 2017 Delaware County (PDF)
- December 21, 2017 Chester County (PDF)
- December 22, 2017 Huntingdon County (PDF)
- December 22, 2017 Lebanon County (PDF)
- December 22, 2017 Cumberland County (PDF)
- January 8, 2018 Chester County (PDF)
- January 25, 2018 Westmoreland County (PDF)
- January 25, 2018 Indiana County (PDF)
- January 25, 2018 Cambria County (PDF)
- January 25, 2018 Cambria County (PDF)
- January 25, 2018 Washington County (PDF)
- February 28, 2018 Cumberland County (PDF)
- March 16, 2018 Lebanon County (PDF)
- March 16, 2018 Blair County (PDF)
- March 19, 2018 Blair County (PDF)
- March 26, 2018 Huntingdon County (PDF)
- March 30, 2018 Perry County (PDF)
- April 6, 2018 Blair County (PDF)
- April 10, 2018 Blair County (PDF)
- April 20, 2018 Lebanon County (PDF)
- May 3, 2018 Delaware County (PDF)
- May 15, 2018 Cambria County (PDF)
- May 24, 2018 Washington County (PDF)
- June 1, 2018 Lebanon County (PDF)
- June 11, 2018 Lebanon County (PDF)
- June 14, 2018 Delaware County (PDF)
- June 15, 2018 Blair County (PDF)
- June 19, 2018 Westmoreland County (PDF)
- June 25, 2018 Cambria County (PDF)
- June 28, 2018 Berks County (PDF)
- June 28, 2018 Lebanon County (PDF)
- June 29, 2018 Washington County (PDF)
- July 9, 2018 Cumberland County (PDF)
- July 16, 2018 Cambria County (PDF)
- July 18, 2018 Washington County (PDF)
- July 19, 2018 Delaware County (PDF)
- July 24, 2018 Cambria County (PDF)
- July 25, 2018 Delaware County (PDF)
- July 25, 2018 Cumberland County (PDF)
- July 31, 2018 Delaware County (PDF)
- August 9, 2018 Delaware County (PDF)
- August 13, 2018 Cambria County (PDF)
- August 13, 2018 Washington County (PDF)
- August 16, 2018 Lebanon County (PDF)
- August 29, 2018 Delaware County (PDF)
- September 5, 2018 Cambria County (PDF)
- September 14, 2018 Cumberland County (PDF)
- September 17, 2018 Berks County (PDF)
- September 18, 2018 Cambria County (PDF)
- September 18, 2018 Cambria County (PDF)
- September 18, 2018 Berks County (PDF)
- October 3, 2018 Blair County (PDF)
- October 9, 2018 Blair County (PDF)
- October 11, 2018 Blair County (PDF)
- October 16, 2018 Blair County (PDF)
- October 18, 2018 Blair County (PDF)
- November 2, 2018 Blair County (PDF)
- November 16, 2018 Chester County (PDF)
- November 26, 2018 Blair County (PDF)
- November 28, 2018 Blair County (PDF)
- February 25, 2019 Cambria County (PDF)
- February 27, 2019 Westmoreland County (PDF)
- April 17, 2019 Cambria County (PDF)
- April 25, 2019 Chester and Delaware Counties (PDF)
- April 29, 2019 Cumberland County (PDF)
- June 13, 2019 Cambria County (PDF)
- July 26, 2019 Cambria County (PDF)
- November 7, 2019 Delaware County (PDF)
- November 7, 2019 Chester County (PDF)
- February 24, 2020 Cumberland County (PDF)
- February 28, 2020 Cumberland County (PDF)
- March 3, 2020 Cumberland County (PDF)
- March 16, 2020 Cumberland County (PDF)
- March 18, 2020 Juniata County (PDF)
- March 23, 2020 Juniata County (PDF)
- May 11, 2020 Cumberland County (PDF)
- May 13, 2020 Blair County (PDF)
- June 11, 2020 Cumberland County (PDF)
- July 22, 2020 Cumberland County (PDF)
- August 13, 2020 Lebanon County (PDF)
- August 20, 2020 Chester County (PDF)
- August 20, 2020 Chester County (PDF)
- August 28, 2020 Lebanon County (PDF)
- September 1, 2020 Lebanon County (PDF)
- September 18, 2020 Lebanon County (PDF)
- September 25, 2020 Lebanon County (PDF)
- October 21, 2020 Lebanon County (PDF)
- April 6, 2021 Delaware County (PDF)
- April 23, 2021 Chester County (PDF)
- June 4, 2021 Chester County (PDF)
- June 16, 2021 Chester County (PDF)
- August 17, 2021 Chester County (PDF)
- September 1, 2021 Chester County (PDF)
- September 10, 2021 Chester County (PDF)
- September 24, 2021 Chester County - response from Sunoco for the August 17, September 1 and September 10, 2021 NOV (PDF)
- January 7, 2022 Chester County – DEP’s request for additional information for the September 1, 2021 NOV (PDF)
- January 21, 2022 Chester County – Sunoco’s response for the January 7, 2022 request for additional information
On February 13, 2017, DEP approved the permit applications from Sunoco Pipeline L.P. for the PA Pipeline Project/Mariner East 2 pipeline project. DEP considered 17 Chapter 105 permit applications and 3 Chapter 102 permit applications for the project.
- E02-1718 - Allegheny County
- E11-352 - Cambria County
- E32-508 - Indiana County
- E63-674 - Washington County
- E65-973 - Westmoreland County
- E31-234 - Huntingdon County
- E34-136 - Juniata County
- E36-945 - Lancaster County
- E38-194 - Lebanon County
- E50-258 - Perry County
- E06-701 - Berks County
- E07-459 - Blair County
- E21-449 - Cumberland County
- E22-619 - Dauphin County
- E23-524 - Delaware County
- E15-862 - Chester County
- E67-920 - York County
- ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin
- ESG0100015001 – Counties: Delaware and Chester
- E&S Permit and Cover Letter (PDF)
- E&S Final Permit (PDF)
On January 19, 2022, DEP received an amendment request to support the dewatering of sediment dredged from a predetermined area of Marsh Creek Lake, as required under the terms of the Consent Order and Agreement entered into between the DEP, DCNR, and Sunoco dated December 6, 2021 at HDD S3-0290, Upper Uwchlan Township, Chester County.
An increase to the limits of disturbance (LOD) of 4.06 acres is being requested. This includes 1.37 acres of proposed bulk earthwork where areas will be topsoiled and graded for the purposes of installing the rock construction entrance, temporary construction road and the preparation of the SMA where the geotubes will be placed. The remaining 2.69 acres will be used for the temporary storage of materials, products or equipment associated dredging and dewatering activity and will not be topsoiled or graded. Utilization of these areas is not proposed to result in earth disturbance but will include erosion and sedimentation (E&S) controls and have been included as part of the LOD.
Information on opportunities to comment on these amendments can be found here.
- January 18, 2022 Application
- January 25, 2022 DEP Incompleteness Letter
- January 26, 2022 Sunoco Response to Comments
- January 26, 2022 Application
- January 27, 2022 DEP Completeness Letter
- February 4, 2022 Press Release
- February 3, 2022 DEP Technical Deficiency Letter to Sunoco
- February 5, 2022 Pennsylvania Bulletin [pg 904]
- April 7, 2022 Ch. 102 Authorization Letter
On April 20, 2021, DEP received Chapter 102 Permit No. ESG0100015001 major amendment request is for the installation of Post Construction Stormwater Management (PCSM) Best Management Practices (BMPs) in the area of Horizontal Directional Drill (HDD) 541 along Middletown Road in Thornbury Township, Delaware County. The PCSM BMPs to be installed include amended soils, 3 detention berms, a diversion berm, and 36-inch perforated storage pipe to collect and detain upstream flow.
- April, 20, 2021 – Sunoco’s Major Amendment request (PDF)
- June 2, 2021 – DEP’s Incompleteness Review letter (PDF)
- July 27, 2021 – Sunoco’s response for Incompleteness Review letter (PDF)
- September 14, 2021 – Sunoco’s updated response for Incompleteness Review letter (PDF)
- October 13, 2021 – Sunoco’s updated response for Incompleteness Review letter (PDF)
- October 15, 2021 – Sunoco’s updated E&S sheets 6.01 & 6.02 (PDF)
- November 3, 2021 – DEP’s Completeness Notification letter (PDF)
- February 16, 2022 – DEP’s Technical Deficiency letter and Thornbury Township Public Comments (PDF)
- March 15, 2022 – Sunoco’s request for an extension to respond to technical deficiency letter and public comments (PDF)
- March 24, 2022 – DEP’s extension request approval (PDF)
- April 13, 2022 – Sunoco’s additional extension request to respond to technical deficiency letter and public comments (PDF)
- April 20, 2022 – DEP’s additional extension request approval (PDF)
- June 15, 2022 – DEP’s extension request approval (PDF)
- August 17, 2022 – Sunoco’s response to technical deficiency letter and public comments (PDF)
- September 13, 2022 – DEP’s technical deficiency letter No. 2 (PDF)
- September 27, 2022 – Sunoco’s response to technical deficiency letter No. 2 (PDF)
On April 7, 2021, DEP received amendment requests for route and installation method changes at HDD S3-0290, Upper Uwchlan Township, Chester County.
The Chapter 102 and Chapter 105 permit amendment requests consist of changes in the horizontal directional drill (HDD) installation method for the 20-inch diameter pipeline to a conventional open trench construction. The new installation, if approved, would use open cut construction methods across Wetland H17, Streams S-H10 and S-H11, under the intersection of Milford Road and Little Conestoga Road and under Highview Road. Additional temporary workspace would be required and an increase to the limits of disturbance of 5.42 acres is being requested.
- April 7, 2021 Chapter 102 Amendment Submission
- April 14, 2021 DEP Incompleteness Letter to Sunoco regarding the Chapter 102 Amendment Application
- April 20, 2021 Sunoco Resubmission in response to April 14, 2021 Incompleteness Letter
- April 26, 2021 DEP Completeness Letter to Sunoco regarding the Chapter 102 Amendment Application
- May 25, 2021, DEP Technical Deficiency letter to Sunoco
- June 1, 2021, Sunoco Responses to May 25, 2021, Technical Deficiency letter regarding Chapter 102
- June 22, 2021, DEP’s Technical Deficiency #2 letter to Sunoco
- June 25, 2021, Sunoco Response to June 22, 2021 Technical Deficiency letter #2
- April 7, 2021 Chapter 105 Amendment Submission
- May 27, 2021, Tetra Tech, Inc., letter to US Fish and Wildlife Service re: PNDI Environmental Review
- December 6, 2021 DEP’s Major Amendment Approval, Chapter 105
- December 6, 2021 DEP’s Major Amendment Approval, Chapter 102
- December 6 2021 Major Amendment Comment Response Document
On May 13, 2019, DEP received a modification request for installation method change at HDD S3-400 Lisa Drive, West Whiteland Township, Chester County. The permit modification request consists of a change in installation method for 20-inch diameter pipeline from a HDD to a Direct Pipe Bore and open trench installation. The direct pipe bore will go under the Exton Bypass (State Route 30), AMTRAK (American Track National Railroad Passenger Corporation), Norfolk Southern Railroad, and wetland WL-K21. The remaining 1,269 feet will be installed via open trench installation. The change in installation method will not result in any increase to the permanent impacts to wetland WL-K21 or other waters of the Commonwealth as set forth in the original Chapter 105 authorization. The modification includes an additional 3.99 acres of LOD.
- Chapter 102 (ESG01000015001) Major Amendment & Chapter 105 (E15-862) Minor Amendment, May 13, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – Lisa Drive November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E15-862 – Lisa Drive November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – Lisa Drive January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – Lisa Drive January 28, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E15-862 – Lisa Drive May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E15-862 – Lisa Drive June 10, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E15-862 – Lisa Drive September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On April 30, 2019, DEP received a modification request for installation method change at PA Turnpike/HDD 0280, Upper Uwchlan Township, Chester County. The permit modification request is to convert the installation method of both the 16 and 20-inch diameter pipelines from a HDD to an open cut installation and one conventional bore. The change in methodology is to minimize impacts to Waters of the Commonwealth and avoid potential future growth requirements of the PA Turnpike 1-76. The modification includes an additional 4.86 acres of LOD.
- Chapter 102 (ESG0100015001) Major Modification, April 30, 2019 (PDF)
- Chapter 105 (E15-862) Major Modification, April 30, 2019 (PDF)
- Sunoco’s Incompleteness Review Response, July 19, 2019 (PDF)
- Chapter 102, ESG0100015001 - Major Modification, August 2, 2019 (PDF)
- Chapter 105, E15-862 - Major Modification, August 2, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – PA Turnpike/0280 November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E15-862 – PA Turnpike/0280 November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – PA Turnpike/0280 January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – PA Turnpike/0280 January 30, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – PA Turnpike/0280 March 11, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – PA Turnpike/0280 April 8, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E15-862 – PA Turnpike/0280 May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E15-862 – PA Turnpike/0280 June 29, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E15-862 - PA Turnpike/0280 September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On March 25, 2019, DEP received a modification request for installation method change at HDD 0620 Middletown Township, Delaware County. This modification is being requested for a change from the HDD installation method for the 20-inch, and portions of the 16-inch, diameter pipelines to a conventional open trench construction through Wetland WL-I1 and Stream S-12, conventional auger bore under Glen Riddle Road, and a direct pipe bore under Riddlewood Drive and the Southeast Pennsylvania Transportation Authority’s (SEPTA) Railroad. The modification includes an additional 5.32 acres of LOD.
- Chapter 102 (ESG0100015001) Minor Amendment & Chapter 105 (E23-524) Major Amendment, March 25, 2019 (PDF)
- Chapter 102 (ESG01000015001) Major Modification, April 25, 2019 (PDF)
- Sunoco’s Incompleteness Review Response, July 24, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – HDD 0620 November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E23-524 – HDD 0620 November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – HDD 0620 January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – HDD 0620 January 30, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – HDD 0620 March 11, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – HDD 0620 April 8, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E23-524 – HDD 0620 May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E23-524 – HDD 0620 June 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E23-524 – HDD 0620 September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On March 7, 2019, DEP received the following request(s) for major permit modification(s) by the Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-Evaluation Reports submitted on March 5, 2019.
- Chapter 105 Water Obstruction and Encroachment Permit (E07-459) in Blair Township, Blair County, for a shift in the HDD entry and exits points to the west of the permitted locations and change in the installation method to a conventional open trench construction through Wetland W-BB58 and a conventional auger bore under Reservoir Road.
- On May 11, 2019, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
On March 1, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-evaluation Reports submitted on December 1, 2017 by Sunoco Pipeline, L.P.
- Chapter 105 Water Obstruction and Encroachment Permit (E50-258) in Toboyne and Jackson Townships, Perry County, for a change in the route and installation method for the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to an open cut installation across Streams S-L6 (Horse Valley Run) and S-Q68 (Unnamed tributary to Horse Valley Run).
- Chapter 102 E&S Permit (ESG03000015002) in Toboyne Township, Perry County, for a change in route and installation method of the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench installation.
On February 4, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-evaluation Reports submitted on December 28, 2017 by Sunoco Pipeline, L.P.
- Chapter 105 Water Obstruction and Encroachment Permit (E50-258) in Toboyne and Jackson Townships, Perry County, for a change in the route and installation method for the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench for a majority of the pipeline route, with a conventional auger bore under Piney Creek Road/High Street (State Route 866).
- Chapter 105 Piney Creek Crossing Major Modification Request, February 1, 2019 (PDF)
- DEP's Incompleteness Review Response, March 7, 2019 (PDF)
- Sunoco's Response to Incompleteness Review, March 21, 2019 (PDF)
- Sunoco's Supplemental Information, April 1, 2019 (PDF)
- Environmental Assessment form, April 2019 (PDF)
- Piney Rapid Assessment map, April 2019 (PDF)
- Piney Site Plan Update map, April 2019 (PDF)
- DEP's Aquatic Resource Impact Table, April 12, 2019 (PDF)
- DEP's Completeness Notification, April 19, 2019 (PDF)
- DEP’s Technical Deficiency Response, August 26, 2019 (PDF)
- Chapter 102 E&S Permit (ESG0300015002) in Woodbury Township, Blair County, for a change in route and installation method of the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench for a majority of the pipeline route, with a conventional auger bore under Piney Creek Road/High Street (State Route 866).
- Chapter 102 Piney Creek Crossing Major Modification Request, February 1, 2019 (PDF)
- DEP’s Major Amendment request, October 30, 2019 (PDF)
- DEP’s Erosion and Sediment Control (E&S), Major Amendment, January 31, 2020 (PDF)
On February 1, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline to reroute and installation method change for the 16- line at the Goldfinch Lane and William Penn Avenue Crossing HDDs.
- Chapter 105 Water Obstruction and Encroachment Permit (E11-352) and Chapter 102 E&S Permit (ESG0500015001-1) in Jackson Township, Cambria County.
- Chapter 102 Major Modification Request (PDF)
- Chapter 105 Joint Permit Application (PDF)
- ESG0500015001-1 Incompleteness Review Response (PDF)
- E11-352-1A – Incompleteness Review Response (PDF)
- DEP’s Technical Deficiency Letter, March 2, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, April 2, 2020 (PDF)
- DEP’s Technical Deficiency Letter, May 5, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, May 19, 2020 (PDF)
- DEP’s Major Amendment Approval, ESG0500015001-1, June 30, 2020 (PDF)
- On April 27, 2019, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
On October 18, 2018, DEP received the following request(s) for major permit modification (s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline.
- Chapter 105 Water Obstruction and Encroachment Permit (E06-701) in Cumru Township, Berks County, for a change in installation method for the 16-inch diameter pipeline from a conventual bore to an open cut installation across Wetland C6, Streams C8 and C9 (unnamed tributaries to Wyomissing Creek).
On August 16, 2018, DEP approved the 2 major permit modification requests as referenced below.
- Permit Modification 1 –
- Permit Modification 2 –
On May 30, 2018, DEP received updated information on the 2 requests for Chapter 102 major permit modifications to the E&S Permit (ESG0100015001) as referenced below.
- Permit Modification 1 - Updated Site Restoration Plans
- Permit Modification 2 - Updated Site Restoration Plans
- On April 21, 2018, DEP provided notice in the PA Bulletin of the extension of the comment period and an associated public hearings.
- On February 10, 2018, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
In October 2017, DEP received 2 requests for a major permit modification to the E&S Permit (ESG0100015001) by the Sunoco Pipeline, L.P. for their Mariner East 2 Pipeline in West Whiteland Township, Chester County. These requests have been coordinated with related HDD Re-Evaluation Reports submitted in November 2017 by Sunoco Pipeline, L.P. These permit modifications are now moving forward in the review process.
- The first request, received October 11, 2017, is entitled Major Modification 1 – East Swedesford Road – HDD S3-381 (PDF). It involves a change in installation methodology for a portion of the project as a result of concerns raised by Aqua America, the local water authority, regarding their Hillside Drive production well along East Swedesford Road.
- The second request, received October 18, 2017, is entitled Major Modification 2 – North Pottstown Pike – HDD S3-370 (PDF). This modification request is a change in installation methodology for a portion of the project following more in-depth hydrogeology analysis and seismic testing.
On February 6, 2017, DEP received updated application material from Sunoco Pipeline, L.P. in response to the technical deficiency items that were provided to the company on January 27, 2017, January 30, 2017 and on February 1, 2017.
- Chapter 102
Project-Wide Modification
DEP received a request for project-wide permit modifications to the E&S Permits (ESG0300015002; ESG0500015001; ESG0100015001) and WO&E Permits (E02-1718; E06-701; E07-459; E11-352; E15-862; E21-449; E22-619; E23-524; E31-234; E32-508; E34-136; E36-945; E38-194; E50-258; E63-674; E65-973; E67-920) by the Sunoco Pipeline, L.P. for their Mariner East 2 Pipeline.
- The request (PDF), received February 27, 2018, is to allow a contractor to change the method of installation of the pipeline at authorized conventional auger bore sites to a cradle bore.
- Upon review of the modification request (PDF), DEP found the project-wide modifications adequate and issued a letter on March 19, 2018 indicating such.
- The request (PDF), received March 14, 2018, is to allow temporary equipment bridges to be in place greater than 1 year.
- Upon review of the modification request (PDF), DEP found the project-wide modifications adequate and issued a letter on March 19, 2018 indicating such.
Comment Response Document
In 2016, DEP held two public comment periods. The Comment Response Document summarizes the comments submitted to DEP by 29,835 commentators during the public participation process. These comments were submitted through the 2 comment periods and 5 public hearings that were held for the project.
- Sunoco PPP - ME2 Comment Response Document-- Part 1 Commentators (PDF)
- Sunoco PPP - ME2 Comment Response Document- Part 2 Comments (PDF)
- Sunoco PPP - ME2 Comment Response Document - Part 3 Appendix (PDF)
Technical Deficiency Letters
On September 6, 2016, DEP sent to Sunoco Pipeline, L.P. technical deficiency letters for the proposed PA Pipeline Project (PPP)/Mariner East II. These letters outlined technical deficiencies that were found during the technical review of the Chapter 105, Water Obstruction and Encroachment Permits and Chapter 102, Erosion and Sediment Control General Permit for Earth Disturbance Associated with Oil and Gas Exploration, Production, Processing or Treatment Operations or Transmission Facilities (ESCGP-2) Notices of Intent (NOI).
On December 5, 2016, DEP received updated application material from Sunoco Pipeline, L.P. in response to the technical deficiency letters that were sent on September 6, 2016.
The following responses to technical deficiency letters and revised permit applications are listed below.
September 6, 2016 | December 5, 2016 |
| |
ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland | ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland |
On August 6, 2016, DEP provided notice in the Pennsylvania Bulletin that the Chapter 102, Erosion and Sediment Control General Permit for Earth Disturbance Associated with Oil and Gas Exploration, Production, Processing or Treatment Operations or Transmission Facilities (ESCGP-2), Notices of Intent (NOI) were under technical review for Sunoco Pipeline, L.P.'s PA Pipeline Project (PPP)/Mariner East II. DEP accepted written comments through Tuesday, September 6, 2016 on the permit applications.
- ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Counties: Delaware and Chester (PDF)
On June 25, 2016, DEP published notice in the Pennsylvania Bulletin of the Chapter 105, Water Obstruction and Encroachment Permits. DEP accepted written comments through Wednesday, August 24, 2016. The permits associated with the comment period included:
- E02-1718 - Allegheny County
- E11-352 - Cambria County
- E32-508 - Indiana County
- E63-674 - Washington County
- E65-973 - Westmoreland County
- E31-234 - Huntingdon County
- E34-136 - Juniata County
- E36-945 - Lancaster County
- E38-194 - Lebanon County
- E50-258 - Perry County
- E67-920 - York County
- E06-701 - Berks County
- E07-459 - Blair County
- E21-449 - Cumberland County
- E22-619 - Dauphin County
- E23-524 - Delaware County
- E15-862 - Chester County
- May 9, 2017 Delaware County (PDF)
- May 17, 2017 Cumberland County (PDF)
- June 5, 2017 Cumberland County (PDF)
- July 20, 2017 Delaware County (PDF)
- July 28, 2017 Allegheny County (PDF)
- July 28, 2017 Indiana County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Westmoreland County (PDF)
- July 28, 2017 Washington County (PDF)
- July 28, 2017 Washington County (PDF)
- August 16, 2017 Lebanon County (PDF)
- August 30, 2017 Dauphin County (PDF)
- September 8, 2017 Chester County (PDF)
- September 12, 2017 Delaware County (PDF)
- October 26, 2017 Blair County (PDF)
- October 26, 2017 Blair County (PDF)
- October 26, 2017 Dauphin County (PDF)
- October 26, 2017 Cumberland County (PDF)
- October 26, 2017 Huntingdon County (PDF)
- October 27, 2017 Lebanon County (PDF)
- October 31, 2017 Lebanon County (PDF)
- November 3, 2017 Chester County (PDF)
- November 3, 2017 Delaware County (PDF)
- November 14, 2017 Dauphin County (PDF)
- November 16, 2017 Berks County (PDF)
- November 16, 2017 Chester County (PDF)
- November 21, 2017 Berks County (PDF)
- November 22, 2017 Blair County (PDF)
- November 27, 2017 Chester County (PDF)
- December 21, 2017 Delaware County (PDF)
- December 21, 2017 Chester County (PDF)
- December 22, 2017 Huntingdon County (PDF)
- December 22, 2017 Lebanon County (PDF)
- December 22, 2017 Cumberland County (PDF)
- January 8, 2018 Chester County (PDF)
- January 25, 2018 Westmoreland County (PDF)
- January 25, 2018 Indiana County (PDF)
- January 25, 2018 Cambria County (PDF)
- January 25, 2018 Cambria County (PDF)
- January 25, 2018 Washington County (PDF)
- February 28, 2018 Cumberland County (PDF)
- March 16, 2018 Lebanon County (PDF)
- March 16, 2018 Blair County (PDF)
- March 19, 2018 Blair County (PDF)
- March 26, 2018 Huntingdon County (PDF)
- March 30, 2018 Perry County (PDF)
- April 6, 2018 Blair County (PDF)
- April 10, 2018 Blair County (PDF)
- April 20, 2018 Lebanon County (PDF)
- May 3, 2018 Delaware County (PDF)
- May 15, 2018 Cambria County (PDF)
- May 24, 2018 Washington County (PDF)
- June 1, 2018 Lebanon County (PDF)
- June 11, 2018 Lebanon County (PDF)
- June 14, 2018 Delaware County (PDF)
- June 15, 2018 Blair County (PDF)
- June 19, 2018 Westmoreland County (PDF)
- June 25, 2018 Cambria County (PDF)
- June 28, 2018 Berks County (PDF)
- June 28, 2018 Lebanon County (PDF)
- June 29, 2018 Washington County (PDF)
- July 9, 2018 Cumberland County (PDF)
- July 16, 2018 Cambria County (PDF)
- July 18, 2018 Washington County (PDF)
- July 19, 2018 Delaware County (PDF)
- July 24, 2018 Cambria County (PDF)
- July 25, 2018 Delaware County (PDF)
- July 25, 2018 Cumberland County (PDF)
- July 31, 2018 Delaware County (PDF)
- August 9, 2018 Delaware County (PDF)
- August 13, 2018 Cambria County (PDF)
- August 13, 2018 Washington County (PDF)
- August 16, 2018 Lebanon County (PDF)
- August 29, 2018 Delaware County (PDF)
- September 5, 2018 Cambria County (PDF)
- September 14, 2018 Cumberland County (PDF)
- September 17, 2018 Berks County (PDF)
- September 18, 2018 Cambria County (PDF)
- September 18, 2018 Cambria County (PDF)
- September 18, 2018 Berks County (PDF)
- October 3, 2018 Blair County (PDF)
- October 9, 2018 Blair County (PDF)
- October 11, 2018 Blair County (PDF)
- October 16, 2018 Blair County (PDF)
- October 18, 2018 Blair County (PDF)
- November 2, 2018 Blair County (PDF)
- November 16, 2018 Chester County (PDF)
- November 26, 2018 Blair County (PDF)
- November 28, 2018 Blair County (PDF)
- February 25, 2019 Cambria County (PDF)
- February 27, 2019 Westmoreland County (PDF)
- April 17, 2019 Cambria County (PDF)
- April 25, 2019 Chester and Delaware Counties (PDF)
- April 29, 2019 Cumberland County (PDF)
- June 13, 2019 Cambria County (PDF)
- July 26, 2019 Cambria County (PDF)
- November 7, 2019 Delaware County (PDF)
- November 7, 2019 Chester County (PDF)
- February 24, 2020 Cumberland County (PDF)
- February 28, 2020 Cumberland County (PDF)
- March 3, 2020 Cumberland County (PDF)
- March 16, 2020 Cumberland County (PDF)
- March 18, 2020 Juniata County (PDF)
- March 23, 2020 Juniata County (PDF)
- May 11, 2020 Cumberland County (PDF)
- May 13, 2020 Blair County (PDF)
- June 11, 2020 Cumberland County (PDF)
- July 22, 2020 Cumberland County (PDF)
- August 13, 2020 Lebanon County (PDF)
- August 20, 2020 Chester County (PDF)
- August 20, 2020 Chester County (PDF)
- August 28, 2020 Lebanon County (PDF)
- September 1, 2020 Lebanon County (PDF)
- September 18, 2020 Lebanon County (PDF)
- September 25, 2020 Lebanon County (PDF)
- October 21, 2020 Lebanon County (PDF)
- April 6, 2021 Delaware County (PDF)
- April 23, 2021 Chester County (PDF)
- June 4, 2021 Chester County (PDF)
- June 16, 2021 Chester County (PDF)
- August 17, 2021 Chester County (PDF)
- September 1, 2021 Chester County (PDF)
- September 10, 2021 Chester County (PDF)
- September 24, 2021 Chester County - response from Sunoco for the August 17, September 1 and September 10, 2021 NOV (PDF)
- January 7, 2022 Chester County – DEP’s request for additional information for the September 1, 2021 NOV (PDF)
- January 21, 2022 Chester County – Sunoco’s response for the January 7, 2022 request for additional information
On February 13, 2017, DEP approved the permit applications from Sunoco Pipeline L.P. for the PA Pipeline Project/Mariner East 2 pipeline project. DEP considered 17 Chapter 105 permit applications and 3 Chapter 102 permit applications for the project.
- E02-1718 - Allegheny County
- E11-352 - Cambria County
- E32-508 - Indiana County
- E63-674 - Washington County
- E65-973 - Westmoreland County
- E31-234 - Huntingdon County
- E34-136 - Juniata County
- E36-945 - Lancaster County
- E38-194 - Lebanon County
- E50-258 - Perry County
- E06-701 - Berks County
- E07-459 - Blair County
- E21-449 - Cumberland County
- E22-619 - Dauphin County
- E23-524 - Delaware County
- E15-862 - Chester County
- E67-920 - York County
- ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin
- ESG0100015001 – Counties: Delaware and Chester
- E&S Permit and Cover Letter (PDF)
- E&S Final Permit (PDF)
On January 19, 2022, DEP received an amendment request to support the dewatering of sediment dredged from a predetermined area of Marsh Creek Lake, as required under the terms of the Consent Order and Agreement entered into between the DEP, DCNR, and Sunoco dated December 6, 2021 at HDD S3-0290, Upper Uwchlan Township, Chester County.
An increase to the limits of disturbance (LOD) of 4.06 acres is being requested. This includes 1.37 acres of proposed bulk earthwork where areas will be topsoiled and graded for the purposes of installing the rock construction entrance, temporary construction road and the preparation of the SMA where the geotubes will be placed. The remaining 2.69 acres will be used for the temporary storage of materials, products or equipment associated dredging and dewatering activity and will not be topsoiled or graded. Utilization of these areas is not proposed to result in earth disturbance but will include erosion and sedimentation (E&S) controls and have been included as part of the LOD.
Information on opportunities to comment on these amendments can be found here.
- January 18, 2022 Application
- January 25, 2022 DEP Incompleteness Letter
- January 26, 2022 Sunoco Response to Comments
- January 26, 2022 Application
- January 27, 2022 DEP Completeness Letter
- February 4, 2022 Press Release
- February 3, 2022 DEP Technical Deficiency Letter to Sunoco
- February 5, 2022 Pennsylvania Bulletin [pg 904]
- April 7, 2022 Ch. 102 Authorization Letter
On April 20, 2021, DEP received Chapter 102 Permit No. ESG0100015001 major amendment request is for the installation of Post Construction Stormwater Management (PCSM) Best Management Practices (BMPs) in the area of Horizontal Directional Drill (HDD) 541 along Middletown Road in Thornbury Township, Delaware County. The PCSM BMPs to be installed include amended soils, 3 detention berms, a diversion berm, and 36-inch perforated storage pipe to collect and detain upstream flow.
- April, 20, 2021 – Sunoco’s Major Amendment request (PDF)
- June 2, 2021 – DEP’s Incompleteness Review letter (PDF)
- July 27, 2021 – Sunoco’s response for Incompleteness Review letter (PDF)
- September 14, 2021 – Sunoco’s updated response for Incompleteness Review letter (PDF)
- October 13, 2021 – Sunoco’s updated response for Incompleteness Review letter (PDF)
- October 15, 2021 – Sunoco’s updated E&S sheets 6.01 & 6.02 (PDF)
- November 3, 2021 – DEP’s Completeness Notification letter (PDF)
- February 16, 2022 – DEP’s Technical Deficiency letter and Thornbury Township Public Comments (PDF)
- March 15, 2022 – Sunoco’s request for an extension to respond to technical deficiency letter and public comments (PDF)
- March 24, 2022 – DEP’s extension request approval (PDF)
- April 13, 2022 – Sunoco’s additional extension request to respond to technical deficiency letter and public comments (PDF)
- April 20, 2022 – DEP’s additional extension request approval (PDF)
- June 15, 2022 – DEP’s extension request approval (PDF)
- August 17, 2022 – Sunoco’s response to technical deficiency letter and public comments (PDF)
- September 13, 2022 – DEP’s technical deficiency letter No. 2 (PDF)
- September 27, 2022 – Sunoco’s response to technical deficiency letter No. 2 (PDF)
On April 7, 2021, DEP received amendment requests for route and installation method changes at HDD S3-0290, Upper Uwchlan Township, Chester County.
The Chapter 102 and Chapter 105 permit amendment requests consist of changes in the horizontal directional drill (HDD) installation method for the 20-inch diameter pipeline to a conventional open trench construction. The new installation, if approved, would use open cut construction methods across Wetland H17, Streams S-H10 and S-H11, under the intersection of Milford Road and Little Conestoga Road and under Highview Road. Additional temporary workspace would be required and an increase to the limits of disturbance of 5.42 acres is being requested.
- April 7, 2021 Chapter 102 Amendment Submission
- April 14, 2021 DEP Incompleteness Letter to Sunoco regarding the Chapter 102 Amendment Application
- April 20, 2021 Sunoco Resubmission in response to April 14, 2021 Incompleteness Letter
- April 26, 2021 DEP Completeness Letter to Sunoco regarding the Chapter 102 Amendment Application
- May 25, 2021, DEP Technical Deficiency letter to Sunoco
- June 1, 2021, Sunoco Responses to May 25, 2021, Technical Deficiency letter regarding Chapter 102
- June 22, 2021, DEP’s Technical Deficiency #2 letter to Sunoco
- June 25, 2021, Sunoco Response to June 22, 2021 Technical Deficiency letter #2
- April 7, 2021 Chapter 105 Amendment Submission
- May 27, 2021, Tetra Tech, Inc., letter to US Fish and Wildlife Service re: PNDI Environmental Review
- December 6, 2021 DEP’s Major Amendment Approval, Chapter 105
- December 6, 2021 DEP’s Major Amendment Approval, Chapter 102
- December 6 2021 Major Amendment Comment Response Document
On May 13, 2019, DEP received a modification request for installation method change at HDD S3-400 Lisa Drive, West Whiteland Township, Chester County. The permit modification request consists of a change in installation method for 20-inch diameter pipeline from a HDD to a Direct Pipe Bore and open trench installation. The direct pipe bore will go under the Exton Bypass (State Route 30), AMTRAK (American Track National Railroad Passenger Corporation), Norfolk Southern Railroad, and wetland WL-K21. The remaining 1,269 feet will be installed via open trench installation. The change in installation method will not result in any increase to the permanent impacts to wetland WL-K21 or other waters of the Commonwealth as set forth in the original Chapter 105 authorization. The modification includes an additional 3.99 acres of LOD.
- Chapter 102 (ESG01000015001) Major Amendment & Chapter 105 (E15-862) Minor Amendment, May 13, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – Lisa Drive November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E15-862 – Lisa Drive November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – Lisa Drive January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – Lisa Drive January 28, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E15-862 – Lisa Drive May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E15-862 – Lisa Drive June 10, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E15-862 – Lisa Drive September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On April 30, 2019, DEP received a modification request for installation method change at PA Turnpike/HDD 0280, Upper Uwchlan Township, Chester County. The permit modification request is to convert the installation method of both the 16 and 20-inch diameter pipelines from a HDD to an open cut installation and one conventional bore. The change in methodology is to minimize impacts to Waters of the Commonwealth and avoid potential future growth requirements of the PA Turnpike 1-76. The modification includes an additional 4.86 acres of LOD.
- Chapter 102 (ESG0100015001) Major Modification, April 30, 2019 (PDF)
- Chapter 105 (E15-862) Major Modification, April 30, 2019 (PDF)
- Sunoco’s Incompleteness Review Response, July 19, 2019 (PDF)
- Chapter 102, ESG0100015001 - Major Modification, August 2, 2019 (PDF)
- Chapter 105, E15-862 - Major Modification, August 2, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – PA Turnpike/0280 November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E15-862 – PA Turnpike/0280 November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – PA Turnpike/0280 January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – PA Turnpike/0280 January 30, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – PA Turnpike/0280 March 11, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – PA Turnpike/0280 April 8, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E15-862 – PA Turnpike/0280 May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E15-862 – PA Turnpike/0280 June 29, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E15-862 - PA Turnpike/0280 September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On March 25, 2019, DEP received a modification request for installation method change at HDD 0620 Middletown Township, Delaware County. This modification is being requested for a change from the HDD installation method for the 20-inch, and portions of the 16-inch, diameter pipelines to a conventional open trench construction through Wetland WL-I1 and Stream S-12, conventional auger bore under Glen Riddle Road, and a direct pipe bore under Riddlewood Drive and the Southeast Pennsylvania Transportation Authority’s (SEPTA) Railroad. The modification includes an additional 5.32 acres of LOD.
- Chapter 102 (ESG0100015001) Minor Amendment & Chapter 105 (E23-524) Major Amendment, March 25, 2019 (PDF)
- Chapter 102 (ESG01000015001) Major Modification, April 25, 2019 (PDF)
- Sunoco’s Incompleteness Review Response, July 24, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 102, ESG0100015001 – HDD 0620 November 22, 2019 (PDF)
- DEP’s Completeness Notification, Chapter 105, E23-524 – HDD 0620 November 22, 2019 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – HDD 0620 January 9, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – HDD 0620 January 30, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 102, ESG0100015001 – HDD 0620 March 11, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 102, ESG0100015001 – HDD 0620 April 8, 2020 (PDF)
- DEP’s Technical Deficiency Letter, Chapter 105, E23-524 – HDD 0620 May 27, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, Chapter 105, E23-524 – HDD 0620 June 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 105, E23-524 – HDD 0620 September 22, 2020 (PDF)
- DEP’s Major Amendment Approval, Chapter 102, ESG0100015001 September 25, 2020 (PDF)
On March 7, 2019, DEP received the following request(s) for major permit modification(s) by the Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-Evaluation Reports submitted on March 5, 2019.
- Chapter 105 Water Obstruction and Encroachment Permit (E07-459) in Blair Township, Blair County, for a shift in the HDD entry and exits points to the west of the permitted locations and change in the installation method to a conventional open trench construction through Wetland W-BB58 and a conventional auger bore under Reservoir Road.
- On May 11, 2019, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
On March 1, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-evaluation Reports submitted on December 1, 2017 by Sunoco Pipeline, L.P.
- Chapter 105 Water Obstruction and Encroachment Permit (E50-258) in Toboyne and Jackson Townships, Perry County, for a change in the route and installation method for the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to an open cut installation across Streams S-L6 (Horse Valley Run) and S-Q68 (Unnamed tributary to Horse Valley Run).
- Chapter 102 E&S Permit (ESG03000015002) in Toboyne Township, Perry County, for a change in route and installation method of the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench installation.
On February 4, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline in coordination with related HDD Re-evaluation Reports submitted on December 28, 2017 by Sunoco Pipeline, L.P.
- Chapter 105 Water Obstruction and Encroachment Permit (E50-258) in Toboyne and Jackson Townships, Perry County, for a change in the route and installation method for the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench for a majority of the pipeline route, with a conventional auger bore under Piney Creek Road/High Street (State Route 866).
- Chapter 105 Piney Creek Crossing Major Modification Request, February 1, 2019 (PDF)
- DEP's Incompleteness Review Response, March 7, 2019 (PDF)
- Sunoco's Response to Incompleteness Review, March 21, 2019 (PDF)
- Sunoco's Supplemental Information, April 1, 2019 (PDF)
- Environmental Assessment form, April 2019 (PDF)
- Piney Rapid Assessment map, April 2019 (PDF)
- Piney Site Plan Update map, April 2019 (PDF)
- DEP's Aquatic Resource Impact Table, April 12, 2019 (PDF)
- DEP's Completeness Notification, April 19, 2019 (PDF)
- DEP’s Technical Deficiency Response, August 26, 2019 (PDF)
- Chapter 102 E&S Permit (ESG0300015002) in Woodbury Township, Blair County, for a change in route and installation method of the 16-inch diameter pipeline from a Horizontal Directional Drill (HDD) to conventional open trench for a majority of the pipeline route, with a conventional auger bore under Piney Creek Road/High Street (State Route 866).
- Chapter 102 Piney Creek Crossing Major Modification Request, February 1, 2019 (PDF)
- DEP’s Major Amendment request, October 30, 2019 (PDF)
- DEP’s Erosion and Sediment Control (E&S), Major Amendment, January 31, 2020 (PDF)
On February 1, 2019, DEP received the following request(s) for major permit modification(s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline to reroute and installation method change for the 16- line at the Goldfinch Lane and William Penn Avenue Crossing HDDs.
- Chapter 105 Water Obstruction and Encroachment Permit (E11-352) and Chapter 102 E&S Permit (ESG0500015001-1) in Jackson Township, Cambria County.
- Chapter 102 Major Modification Request (PDF)
- Chapter 105 Joint Permit Application (PDF)
- ESG0500015001-1 Incompleteness Review Response (PDF)
- E11-352-1A – Incompleteness Review Response (PDF)
- DEP’s Technical Deficiency Letter, March 2, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, April 2, 2020 (PDF)
- DEP’s Technical Deficiency Letter, May 5, 2020 (PDF)
- Sunoco’s Technical Deficiency Response, May 19, 2020 (PDF)
- DEP’s Major Amendment Approval, ESG0500015001-1, June 30, 2020 (PDF)
- On April 27, 2019, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
On October 18, 2018, DEP received the following request(s) for major permit modification (s) by Sunoco Pipeline, L.P. for the Mariner East 2 Pipeline.
- Chapter 105 Water Obstruction and Encroachment Permit (E06-701) in Cumru Township, Berks County, for a change in installation method for the 16-inch diameter pipeline from a conventual bore to an open cut installation across Wetland C6, Streams C8 and C9 (unnamed tributaries to Wyomissing Creek).
On August 16, 2018, DEP approved the 2 major permit modification requests as referenced below.
- Permit Modification 1 –
- Permit Modification 2 –
On May 30, 2018, DEP received updated information on the 2 requests for Chapter 102 major permit modifications to the E&S Permit (ESG0100015001) as referenced below.
- Permit Modification 1 - Updated Site Restoration Plans
- Permit Modification 2 - Updated Site Restoration Plans
- On April 21, 2018, DEP provided notice in the PA Bulletin of the extension of the comment period and an associated public hearings.
- On February 10, 2018, DEP provided notice of the Request for Permit Modifications in the PA Bulletin.
In October 2017, DEP received 2 requests for a major permit modification to the E&S Permit (ESG0100015001) by the Sunoco Pipeline, L.P. for their Mariner East 2 Pipeline in West Whiteland Township, Chester County. These requests have been coordinated with related HDD Re-Evaluation Reports submitted in November 2017 by Sunoco Pipeline, L.P. These permit modifications are now moving forward in the review process.
- The first request, received October 11, 2017, is entitled Major Modification 1 – East Swedesford Road – HDD S3-381 (PDF). It involves a change in installation methodology for a portion of the project as a result of concerns raised by Aqua America, the local water authority, regarding their Hillside Drive production well along East Swedesford Road.
- The second request, received October 18, 2017, is entitled Major Modification 2 – North Pottstown Pike – HDD S3-370 (PDF). This modification request is a change in installation methodology for a portion of the project following more in-depth hydrogeology analysis and seismic testing.
On February 6, 2017, DEP received updated application material from Sunoco Pipeline, L.P. in response to the technical deficiency items that were provided to the company on January 27, 2017, January 30, 2017 and on February 1, 2017.
- Chapter 102
Project-Wide Modification
DEP received a request for project-wide permit modifications to the E&S Permits (ESG0300015002; ESG0500015001; ESG0100015001) and WO&E Permits (E02-1718; E06-701; E07-459; E11-352; E15-862; E21-449; E22-619; E23-524; E31-234; E32-508; E34-136; E36-945; E38-194; E50-258; E63-674; E65-973; E67-920) by the Sunoco Pipeline, L.P. for their Mariner East 2 Pipeline.
- The request (PDF), received February 27, 2018, is to allow a contractor to change the method of installation of the pipeline at authorized conventional auger bore sites to a cradle bore.
- Upon review of the modification request (PDF), DEP found the project-wide modifications adequate and issued a letter on March 19, 2018 indicating such.
- The request (PDF), received March 14, 2018, is to allow temporary equipment bridges to be in place greater than 1 year.
- Upon review of the modification request (PDF), DEP found the project-wide modifications adequate and issued a letter on March 19, 2018 indicating such.
Comment Response Document
In 2016, DEP held two public comment periods. The Comment Response Document summarizes the comments submitted to DEP by 29,835 commentators during the public participation process. These comments were submitted through the 2 comment periods and 5 public hearings that were held for the project.
- Sunoco PPP - ME2 Comment Response Document-- Part 1 Commentators (PDF)
- Sunoco PPP - ME2 Comment Response Document- Part 2 Comments (PDF)
- Sunoco PPP - ME2 Comment Response Document - Part 3 Appendix (PDF)
Technical Deficiency Letters
On September 6, 2016, DEP sent to Sunoco Pipeline, L.P. technical deficiency letters for the proposed PA Pipeline Project (PPP)/Mariner East II. These letters outlined technical deficiencies that were found during the technical review of the Chapter 105, Water Obstruction and Encroachment Permits and Chapter 102, Erosion and Sediment Control General Permit for Earth Disturbance Associated with Oil and Gas Exploration, Production, Processing or Treatment Operations or Transmission Facilities (ESCGP-2) Notices of Intent (NOI).
On December 5, 2016, DEP received updated application material from Sunoco Pipeline, L.P. in response to the technical deficiency letters that were sent on September 6, 2016.
The following responses to technical deficiency letters and revised permit applications are listed below.
September 6, 2016 |
December 5, 2016 |
| |
ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland |
ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland |
On August 6, 2016, DEP provided notice in the Pennsylvania Bulletin that the Chapter 102, Erosion and Sediment Control General Permit for Earth Disturbance Associated with Oil and Gas Exploration, Production, Processing or Treatment Operations or Transmission Facilities (ESCGP-2), Notices of Intent (NOI) were under technical review for Sunoco Pipeline, L.P.'s PA Pipeline Project (PPP)/Mariner East II. DEP accepted written comments through Tuesday, September 6, 2016 on the permit applications.
- ESG0500015001 – Counties: Allegheny, Cambria, Indiana, Washington and Westmoreland (PDF)
- ESG0300015002 – Counties: Huntingdon, Juniata, Lancaster, Lebanon, Perry, York, Berks, Blair, Cumberland and Dauphin (PDF)
- ESG0100015001 – Counties: Delaware and Chester (PDF)
On June 25, 2016, DEP published notice in the Pennsylvania Bulletin of the Chapter 105, Water Obstruction and Encroachment Permits. DEP accepted written comments through Wednesday, August 24, 2016. The permits associated with the comment period included:
- E02-1718 - Allegheny County
- E11-352 - Cambria County
- E32-508 - Indiana County
- E63-674 - Washington County
- E65-973 - Westmoreland County
- E31-234 - Huntingdon County
- E34-136 - Juniata County
- E36-945 - Lancaster County
- E38-194 - Lebanon County
- E50-258 - Perry County
- E67-920 - York County
- E06-701 - Berks County
- E07-459 - Blair County
- E21-449 - Cumberland County
- E22-619 - Dauphin County
- E23-524 - Delaware County
- E15-862 - Chester County