District 11 Projects - Allegheny County

​​​I-79 – Route 60 (Crafton / Moon Run) to I-376 (Airport / Pittsburgh)​​​

Project Overview

County: Allegheny
State Route: 0079
Local Name: Interstate 79
Project Type: Highway Restoration​
Start: April 2024
End: May 2025
Last Updated: April 4, 2024

Work on this highway restoration project in Robinson and Kennedy townships will begin in April 2024. The project begins at the I-376 Airport/Pittsburgh (Exit 59 A/B) interchange and continues approximately one-half mile north of the Route 60 Moon Run/Crafton (Exit 60 A/B) interchange. The work includes concrete pavement patching, guiderail and cable barrier replacement, highway lighting and signing updates, drainage work, pavement markings and other miscellaneous construction activities on mainline I-79 and ten ramps (four at the I-376 interchange and six ramps at the Route 60 interchange). There will be bridge preservation work on six structures (northbound and southbound I-79 bridges over I-376, Route 60, and Campbells Run Road), including concrete deck overlays, replacement of seals at expansion dams and deck joints, substructure concrete repairs, cleaning of bridge bearings and spot painting of the northbound and southbound I-79 steel I-beam bridges over I-376. The majority of the roadway work along mainline I-79 will be performed under short-term, single-lane closures during nighttime restrictions. There will be long-term lane restrictions in place for the bridge work, including six weekend-long lane restrictions. Additionally, there will be milling and paving operations on Route 60 between Lorish Road and Old Steubenville Pike, preservation work of six existing sign structures (one on northbound I-79 and five on southbound I-79) as well as concrete repairs and scour protection of two arch culverts underneath mainline I-79 and several ramps.  The project is anticipated to conclude in late spring of 2025.

Project Statistics

Cost: $19.36 million
Contractor: Golden Triangle Construction

Project Update

4/4/2024 - PennDOT District 11 is announcing overnight ramp closures of the I-376 West/East interchange ramps to northbound I-79 in Robinson Township, Allegheny County will begin Monday, April 8 weather permitting.

Press Releases

Contact Information

Nicole E. Haney
Press Office
(412) 429-5011
nhaney@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the PennDOT Project Manager listed above.