Project Overview

County: Wyoming County
Municipality: Nicholson Township
Route: 1015
Local Name: Field Brook Road
Project Type: Bridge Replacement
Start Month: May 2026
End Month: September 2026
Last Updated: January 2024
Designer: RK&K, LLP

The Pennsylvania Department of Transportation (PennDOT) invites the public to a virtual online plans display for the bridge replacement carrying SR 1015 (Field Brook Road) over Field Brook in Nicholson Township, Wyoming County.

SR 1015 (Field Brook Road) crosses over Field Brook in Wyoming County. The existing structure is a 1-span Steel I-Beam Stringer Bridge built in 1941 with a span length of 32'. The existing bridge is currently weight restricted and posted for a limit of 4 tons.

This bridge replacement will alleviate any current weight restrictions and provide a structure that meets current design standards. The proposed bridge is a two-lane bridge with 2-10' lanes and 2-3' shoulders. This project will also include approximately 300' of full depth paving on the roadway approaches and relocation of the existing 6" Sunoco gas transmission line.

The bridge is anticipated to be closed during the 2026 construction season for approximately 3 months. During construction, traffic will be detoured using state roads. The 14.5-mile detour will include SR 92, SR 1011 (W Nicholson Rd), SR 2001, and SR 2003. Access to driveways and businesses within and near the work area will remain open during construction.

The purpose of the plans display is to introduce the project, describe the maintenance of traffic during construction, and receive public input regarding any questions or concerns with the project. The plans will be made available to the public from March 25, 2024 to April 22, 2024. 

The public is encouraged to respond to the public questionnaire and provide comments by clicking on the Public Questionnaire to be completed by hand and mailed to the address at the bottom of the form.

The project documents will be made available in alternative languages or formats if requested. If you need translation/interpretation services or have special needs or have special concerns that require individual attention, please contact PennDOT Project Manager Joe Spall, at jospall@pa.gov or 570.335.9242.

Traffic Control

From points east of the bridge, head southeast along Field Brook Road to the Field Brook Rd and PA State Route 92 intersection. At the intersection, turn right onto PA State Route 92 and travel 1.7 miles. At PA State Route 92 and W. Nicholson Road intersection, turn right onto W. Nicholson Road and travel 3.0 miles. At intersection of W. Nicholson Road and State Route 1011 / 2001 turn right and travel 3.5 miles to intersection of State Route 1011 / 2001 and Field Brook Road. 

From points west of the bridge, head north along Field Brook Road to the Field Brook Road and State Route 1011 / 2001. At intersection of Field Brook Road and State Route 1011 / 2001, turn left and travel 3.5 miles. At intersection of State Route 1011 / 2001 and W. Nicholson Road turn left and travel 3.0 miles along W. Nicholson Road. At W. Nicholson Road and PA State Route 92 intersection, turn left onto PA State Route 92 and travel 1.7 miles to intersection of PA State Route 92 and Field Brook Road

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.​

Contact Information

Joseph Spall
Project Manager
570-335-9242
jospall@pa.gov

Jessica Ruddy
Press Officer
(570) 963-4044
jeruddy@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the PennDOT Project Manager listed above.