Project Overview
County: Susquehanna
Project Type: Bridge Replacement Project
Start: September 2024
End: Winter 2025
Last Updated: April 11, 2024
This project is the replacement of an existing culvert with a concrete box culvert and end sections. The project also includes full depth pavement replacement, milling and resurfacing, drainage, guide rail, and other miscellaneous construction.
Traffic Control
Traffic control will be maintained under a 8.3 mile detour.
Contact Information
Steve Valenti
PennDot Project Manager
c-svalenti@pa.gov
Jessica Ruddy
PennDOT Press Officer
570-963-4044
jeruddy@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the PennDOT Project Manager listed above.