​​2024 ​Detours​

Bedford County


Blair County


Cambria County



Fulton County


Huntingdon County



Somerset County





  • Scope: Structure replacement with 1-span prestressed concrete spread box beam bridge
    • Bid with T-305 Bennett Road Bridge
  • Detour Length: 8.7 miles
  • Construction Timeframe: April - November 2024
  • Anticipated Detour Implementation Date: April 2024
  • Anticipated Date Detour to be Lifted: September 2024
  • Contractor: Wen-Brook Contracting, Inc.
  • Current Contract: $740,762



  • Scope: Structure Rehabilitation
    • Bid with T-317 Mountain Road Bridge
  • Detour Length: (Using Mountain Road Bridge Detour) 8.7 miles
  • Construction Timeframe: April - November 2024
  • Anticipated Detour Implementation Date: April 2024
  • Anticipated Date Detour to be Lifted: April 2024
  • Contractor: Wen-Brooke Contracting, Inc.
  • Current Contract: $740,762

View the T-305 Bennett Road Bridge Project Detour Map​ (PDF).



  • Scope: Pavement preservation (5.4 miles), drainage improvements, guide rail upgrades, safety improvement to Lake Gordon Intersection and Narrow Lane, Three structure rehabilitations
  • Detour Lengths: Lake Gordon Rd. - 14 miles (14-day max, July 2024) T-337 Narrow Lane - 5.9 miles (28-day max, August - September 2024)
  • Detour Implementation Dates: Narrow Lane - May 13, 2024
  • Construction Timeframe: April 2024 - October 2025
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $4,425,000

View U.S. 220 - Lake Gordon Road and T-337 Narrow Lane Project Detour Map​ (PDF).​​




  • Scope: Bridge rehabilitation, concrete patching, thin lift overlay, auxiliary lane construction and guide rail upgrades. (8.8 miles)
  • Detour lengths: Grazierville Interchange - 14.1 miles; Tyrone Interchange (Southern - 7.8 miles) (Northern - 5.9 miles)
  • Construction Timeframe: April 2024 - October 2025
  • ​Detour Implementation Dates: Vary by interchange
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $23,350,000


  • Scope: Bridge replacement
  • Detour Length: 6.5 miles
  • Construction Timeframe: September 2023 - November 2024
  • Anticipated Detour implementation Date: Gates Hill Truck Detour: April 2024; Gates Hill Road Detour: July 2024
  • Contractor: Beech Construction, Inc.
  • Current Contract: $4,780,295





  • Scope: Bridge Replacement
  • Detour Length: 15.9 miles
  • Construction Timeframe: June 2024 - November 2024
  • Anticipated Detour Implementation Date: June 11, 2024
  • Anticipated Date Detour to be Lifted: October 8, 2024
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $1,384,000


  • Scope: Bridge rehab - Design/Build
  • Detour Length: East and Westboud Lanes 6.3 miles
  • Construction Timeframe: As early as Spring 2024 - August 2025
  • Anticipated Detour Implementation Date: TBD
  • Anticipated Date Detour to be Lifted: TBD
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $3,994,000


View the Route 2019 (Level Road) over U.S. 22 Bridge D/B Project Map​ (PDF).​


  • Scope: Bridge Rehabilitation
  • Detour Length: 1.4 miles
  • Construction Timeframe: January 2024 - October 2024
  • Detour Implementation Date: January 2024
  • Anticipated Date Detour to be Lifted: August 21, 2024
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $2,393,000

​View the Maple Ave. over w/Branch Suquehanna River Project Map (PDF).


  • Scope: Bridge Rehabilitation
    • Bid with Route 3024 under 8' Pipe Project
  • Detour Length: 5.2 miles
  • Construction Estimate: Less than $1 million
  • Anticipated Bid Opening: 2nd Quarter 2024


View the  Route 3024 (Railroad Street) over Sunshine Coal Company Drift Project Map​ (PDF).


  • Scope: Under 8' Pipe Replacement
    • ​Bid w/Route 3024 over Sunshine Coal Company Drift
  • Detour Length: 5.2 miles
  • Construction Estimate: $1-5 million
  • Anticipated Bid Opening: 2nd Quarter 2024


View the Route 3024 (Railroad Street) under 8' Pipe Replacement Project Detour Map (PDF).


  • Scope: Resurfacing, Structure Rehab and Replacement, Drainage and Guiderail Upgrades
  • Detour Length: 10 miles (Exit 163 (Amaranth) eastbound
  • Construction Timeframe: April 2023 - August 2027
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: August 2024
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $30,990,126


View the I-70 Amaranth to Maryland State Line Project Detour Map (PDF).



  • Scope: Replace Corrugated Steel Plate Pipe Arch w/17'x11' Precast RC Box Culvert
  • Detour Length: 3.5 miles (80 days)
  • Construction Timeframe: March 2024 - September 2024
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: August 2024
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $1,154,111


View the T-340 (Fairview Road) over Indian Grave Run Project Detour Map (PDF).​


  • Scope: Repalce RC Arch w/Precast RC Box Culvert & Bethel Church Road Intersection Improvements
  • Detour Length: U.S. 522 detour 16.2 miles, 7-day max; T-328 Bethel Church Road detour 12.6 miles, 58-day max.
  • Anticipated Detour Implementation Dates: U.S. 522 June 2024, T-328 Bethel Church Road June - August 2024
  • Construction Timeframe: January 2024 - Auust 2024
  • Contractor: Charles J. Merlo, Inc.
  • Currrent Contract: $1,413,000


View the U.S. 522 White Oak Run Project Detour Maps (PDF).


  • Scope: Structure Replacement
  • Detour Lengths: Auto - 3.3 miles; Truck - 25.3 miles
  • Construction Estimate: $1,785,000


View the PA 915 over Unnamed Tributary to Laurel Fork Project Detour Maps (PDF).


  • Scope: Bridge Replacement
  • Detour Length: 5.1 miles
  • Construction Timeframe: June 2024 - October 2024
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: October 2024
  • Contractor: Jay Fulkroad & Sons Inc.
  • Current Contract: $813,278


View the T-573 (Wilson Road) Bridge Replacement Project Detour Map (PDF).

  • Scope: Resurfacing (6.4 miles), 2 Box Culvert Replacements, Drainage Upgrades, Slide Remediation
  • Detour Length: 17 miles
  • Construction Timeframe: March 2024 - November 2024
  • Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: October 2024
  • Contractor: Plum Contracting, Inc.
  • Current Contract: $15,649,128


View the PA 403 - U.S. 219 to A 985 Resurfacing Project Detour Map (PDF). 


  • Scope: Three Bridge Replacements, One Culvert Replacement
  • Detour Length: 12 miles
  • Construction Timeframe: April 2024 - September 2025
  • Anticipated Detour Implementation Dates: June 11, 2024 & June 10, 2025
  • Anticipated Dates Detours to be Lifted: August 23, 2024 & Auust 22, 2025
  • Contractor: C.H. & D. Enterprises, Inc.
  • Current Contract: $2,566,257


View the Route 3001 Cucumber Run Bridges Project Detour Map​ (PDF).


  • Scope: Resurfacing, Drainage, and Guide Rail Upgrades
  • Detour Length: 51 miles
  • Construction Timeframe: May 2024 - October 2024
  • Anticipated Detour Implementation Dates: TBD - two detours with a 4-day duration and one detour with a 5-day duration
  • Anticipated Dates Detours to be Lifted: TBD
  • Contractor: New Enterprise Stone and Lime Co.
  • Current Contract: $3,349,111


View the PA 31 Barn Swallow Road to Somerset Borough Line Project Detour Map (PDF).