When research projects are nearing completion, the RPM section determines if the project results can be implemented. In determining the results for implementation into business practices, PennDOT evaluates how the product or process can maximize the department's return on research investments and advance its strategic goals and objectives.
-
1
Pre-Project Close-Out Meeting
-
2
Project Close-Out Meeting
-
3
Internal PennDOT Project Scoping Meeting
-
4
Implementation Project Scoping Meeting
-
5
Development of Scope of Work
-
6
Amendment of Work Order
-
7
Implementation Kick Off Meeting
-
8
Implementation Activities
-
9
Implementation After Action Review