2025 Detours

Somerset County


  • Scope: Paving, the renovation of multiple bridge-structures, and drainage, guide rail and signage upgrades along five (5) miles of U.S. 219 in Somerset County. 
  • Detours: During the Route 4102 (Sechler Road) bridge-structure renovation, a 6.5-mile detour will divert traffic to Route 281 to Route 4026 (Lake Road) to Route 601 (North Center Avenue) to Gilmour Road (T-861).     During the Route 4104 (Critchfield Road / T-626) bridge-structure renovation, a 2.4-mile detour will divert traffic to Route 601 (Penn Avenue) to Route 4004 (Bicycle Road) to Morris Road (T-548).​
  • Construction Timeframe: August 2024 - October 2026
  • ​Detour Implementation Dates: April 7, 2025 for appox. 30 days
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $25,000,000.00

 

Cambria County


  • Scope: Bridge rehab - Design/Build
  • Detour Length: East and Westboud Lanes 6.3 miles
  • Construction Timeframe: As early as Spring 2024 - August 2025
  • Anticipated Detour Implementation Date: April 7, 2025
  • Anticipated Date Detour to be Lifted: May 9, 2025
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $3,994,000

 

View the Route 2019 (Level Road) over U.S. 22 Bridge D/B Project Map​ (PDF).​

Blair County


  • Scope: Bridge rehabilitation - 12th Street and 16th Street will be closed.
  • Detour lengths: Less than 1 mile for each. For the 12th Street bridge project, the detour uses Pleasant Valley Boulevard, 10th Street, 13th Street, Adams Avenue, and Valley View Boulevard. For the 16th Street project, the detour uses Jaggard Street, Valley View Boulevard, 15th Street and Pleasant Valley Boulevard.
  • Construction Timeframe: April 2025 - May 2025
  • ​Detour Implementation Dates: April 8, 2025
  • Contractor: Cottle’s Asphalt Maintenance, Inc., Everett, Pa.
  • Current Contract: $524,135.35

 

 

 

 

 





2024 Detours

Cambria County


  • Scope: Bridge replacement
  • Detour Length: 6.5 miles
  • Construction Timeframe: September 2023 - November 2024
  • Anticipated Detour implementation Date: Gates Hill Truck Detour: April 2024; Gates Hill Road Detour: July 2024
  • Contractor: Beech Construction, Inc.
  • Current Contract: $4,780,295




  • Scope: Bridge Replacement
  • Detour Length: 15.9 miles
  • Construction Timeframe: June 2024 - November 2024
  • Anticipated Detour Implementation Date: June 11, 2024
  • Anticipated Date Detour to be Lifted: October 8, 2024
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $1,384,000


  • Scope: Bridge rehab - Design/Build
  • Detour Length: East and Westboud Lanes 6.3 miles
  • Construction Timeframe: As early as Spring 2024 - August 2025
  • Anticipated Detour Implementation Date: TBD
  • Anticipated Date Detour to be Lifted: TBD
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $3,994,000


View the Route 2019 (Level Road) over U.S. 22 Bridge D/B Project Map​ (PDF).​


  • Scope: Bridge Rehabilitation
  • Detour Length: 1.4 miles
  • Construction Timeframe: January 2024 - October 2024
  • Detour Implementation Date: January 2024
  • Anticipated Date Detour to be Lifted: August 21, 2024
  • Contractor: Charles J. Merlo, Inc.
  • Current Contract: $2,393,000

​View the Maple Ave. over w/Branch Suquehanna River Project Map (PDF).


  • Scope: Bridge Rehabilitation
    • Bid with Route 3024 under 8' Pipe Project
  • Detour Length: 5.2 miles
  • Construction Estimate: Less than $1 million
  • Anticipated Bid Opening: 2nd Quarter 2024


View the  Route 3024 (Railroad Street) over Sunshine Coal Company Drift Project Map​ (PDF).


  • Scope: Under 8' Pipe Replacement
    • ​Bid w/Route 3024 over Sunshine Coal Company Drift
  • Detour Length: 5.2 miles
  • Construction Estimate: $1-5 million
  • Anticipated Bid Opening: 2nd Quarter 2024


View the Route 3024 (Railroad Street) under 8' Pipe Replacement Project Detour Map (PDF).

Bedford County


  • Scope: Structure replacement with 1-span prestressed concrete spread box beam bridge
    • Bid with T-305 Bennett Road Bridge
  • Detour Length: 8.7 miles
  • Construction Timeframe: April - November 2024
  • Anticipated Detour Implementation Date: April 2024
  • Anticipated Date Detour to be Lifted: September 2024
  • Contractor: Wen-Brook Contracting, Inc.
  • Current Contract: $740,762



  • Scope: Structure Rehabilitation
    • Bid with T-317 Mountain Road Bridge
  • Detour Length: (Using Mountain Road Bridge Detour) 8.7 miles
  • Construction Timeframe: April - November 2024
  • Anticipated Detour Implementation Date: April 2024
  • Anticipated Date Detour to be Lifted: April 2024
  • Contractor: Wen-Brooke Contracting, Inc.
  • Current Contract: $740,762

View the T-305 Bennett Road Bridge Project Detour Map​ (PDF).



  • Scope: Pavement preservation (5.4 miles), drainage improvements, guide rail upgrades, safety improvement to Lake Gordon Intersection and Narrow Lane, Three structure rehabilitations
  • Detour Lengths: Lake Gordon Rd. - 14 miles (14-day max, July 2024) T-337 Narrow Lane - 5.9 miles (28-day max, August - September 2024)
  • Detour Implementation Dates: Narrow Lane - May 13, 2024
  • Construction Timeframe: April 2024 - October 2025
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $4,425,000

View U.S. 220 - Lake Gordon Road and T-337 Narrow Lane Project Detour Map​ (PDF).​​



Blair County


  • Scope: Bridge rehabilitation, concrete patching, thin lift overlay, auxiliary lane construction and guide rail upgrades. (8.8 miles)
  • Detour lengths: Grazierville Interchange - 14.1 miles; Tyrone Interchange (Southern - 7.8 miles) (Northern - 5.9 miles)
  • Construction Timeframe: April 2024 - October 2025
  • ​Detour Implementation Dates: Vary by interchange
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $23,350,000

Fulton County


  • Scope: Resurfacing, Structure Rehab and Replacement, Drainage and Guiderail Upgrades
  • Detour Length: 10 miles (Exit 163 (Amaranth) eastbound
  • Construction Timeframe: April 2023 - August 2027
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: August 2024
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $30,990,126


View the I-70 Amaranth to Maryland State Line Project Detour Map (PDF).



  • Scope: Replace Corrugated Steel Plate Pipe Arch w/17'x11' Precast RC Box Culvert
  • Detour Length: 3.5 miles (80 days)
  • Construction Timeframe: March 2024 - September 2024
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: August 2024
  • Contractor: New Enterprise Stone & Lime Co., Inc.
  • Current Contract: $1,154,111


View the T-340 (Fairview Road) over Indian Grave Run Project Detour Map (PDF).​


  • Scope: Repalce RC Arch w/Precast RC Box Culvert & Bethel Church Road Intersection Improvements
  • Detour Length: U.S. 522 detour 16.2 miles, 7-day max; T-328 Bethel Church Road detour 12.6 miles, 58-day max.
  • Anticipated Detour Implementation Dates: U.S. 522 June 2024, T-328 Bethel Church Road June - August 2024
  • Construction Timeframe: January 2024 - Auust 2024
  • Contractor: Charles J. Merlo, Inc.
  • Currrent Contract: $1,413,000


View the U.S. 522 White Oak Run Project Detour Maps (PDF).


  • Scope: Structure Replacement
  • Detour Lengths: Auto - 3.3 miles; Truck - 25.3 miles
  • Construction Estimate: $1,785,000


View the PA 915 over Unnamed Tributary to Laurel Fork Project Detour Maps (PDF).

Huntingdon County


  • Scope: Bridge Replacement
  • Detour Length: 5.1 miles
  • Construction Timeframe: June 2024 - October 2024
  • Anticipated Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: October 2024
  • Contractor: Jay Fulkroad & Sons Inc.
  • Current Contract: $813,278


View the T-573 (Wilson Road) Bridge Replacement Project Detour Map (PDF).

Somerset County

  • Scope: Resurfacing (6.4 miles), 2 Box Culvert Replacements, Drainage Upgrades, Slide Remediation
  • Detour Length: 17 miles
  • Construction Timeframe: March 2024 - November 2024
  • Detour Implementation Date: June 2024
  • Anticipated Date Detour to be Lifted: October 2024
  • Contractor: Plum Contracting, Inc.
  • Current Contract: $15,649,128


View the PA 403 - U.S. 219 to A 985 Resurfacing Project Detour Map (PDF). 


  • Scope: Three Bridge Replacements, One Culvert Replacement
  • Detour Length: 12 miles
  • Construction Timeframe: April 2024 - September 2025
  • Anticipated Detour Implementation Dates: June 11, 2024 & June 10, 2025
  • Anticipated Dates Detours to be Lifted: August 23, 2024 & Auust 22, 2025
  • Contractor: C.H. & D. Enterprises, Inc.
  • Current Contract: $2,566,257


View the Route 3001 Cucumber Run Bridges Project Detour Map​ (PDF).


  • Scope: Resurfacing, Drainage, and Guide Rail Upgrades
  • Detour Length: 51 miles
  • Construction Timeframe: May 2024 - October 2024
  • Anticipated Detour Implementation Dates: TBD - two detours with a 4-day duration and one detour with a 5-day duration
  • Anticipated Dates Detours to be Lifted: TBD
  • Contractor: New Enterprise Stone and Lime Co.
  • Current Contract: $3,349,111


View the PA 31 Barn Swallow Road to Somerset Borough Line Project Detour Map (PDF).