Project Status
Step 3 of 4
Construction
Next Step: Completed
Project Overview
County: Allegheny
Municipality: Franklin Park and Marshall Township
State Route: I-79 and 910
Local Name: Wexford Interchange
Project Type: Improvement
Construction Start: August 2025
Proposed Construction End: September 2027
Last Updated: 10/02/2025
The $46.5 million I-79, Route 910 Wexford Interchange project will include new construction of a full offset single-point urban interchange (SPUI) at the I-79/Route 910 Wexford Interchange. The project limits along I-79 are from approximately 1.5 miles north of the I-79/I-279 split to Mingo Road and the limits on Route 910 are between Nicholson Road Drive and Brandt School Road/VIP in Franklin Park Borough and Marshall Township. Bridge work includes two new flyover structures over I-79, as well as sign structures and bridge preservation to the existing bridge carrying Route 910 over I-79. Other work includes traffic signal improvements, new highway lighting, minor ITS upgrades, drainage work, signing/pavement marking and guide rail updates, and other miscellaneous construction. During construction, three lanes of traffic in each direction are expected during peak travel times, as well as temporary ramps to maintain access for most of the project. Additionally, short-term lane and shoulder closures will be utilized. Beams for the new structures will be set during overnight traffic stoppages of I-79 northbound. While I-79 southbound will be detoured overnight using the existing southbound off- and on-ramps during beam setting. The project is anticipated to continue through the 2027 construction season. Golden Triangle Construction Company is the prime contractor.
Location Map
-
10/02/2025 Interstate 79/Route 910 Wexford Interchange Ramp Restrictions Next Week in Allegheny County The southbound on-ramp to I-79 from Route 910/Wexford Bayne Road will be reduced to a single-lane of traffic from 9:00 AM to 3:00 PM each day, Monday through Friday, to allow utility relocation work to occur. Additionally, to allow the work to occur on the on-ramp, there will be a closure of one of the two turning lanes from westbound Route 910/Wexford Bayne Road to the southbound I-79 on-ramp.
-
09/26/2025 Interstate 79/Route 910 Wexford Interchange Shoulder Restrictions Continue Next Week in Allegheny County Shoulder restrictions will occur each weekday from 9:00 AM to 3:00 PM through mid-October
-
09/24/2025 REMINDER: Interstate 79/Route 910 Wexford Interchange Project Public Meeting Today The Pennsylvania Department of Transportation (PennDOT) in cooperation with the Federal Highway Administration (FHWA), JMT, Inc., WRA, LLP and Golden Triangle Construction Company are pleased to invite you to attend a public meeting being conducted today, Wednesday, September 24 to discuss the I-79/Route 910 Wexford Interchange Project in Franklin Park Borough and Marshall Township, Allegheny County.
-
09/19/2025 Interstate 79/Route 910 Wexford Interchange Phase Change Begins Saturday night in Allegheny County The Pennsylvania Department of Transportation (PennDOT) is announcing the next phase of work for the Interstate 79/Route 910 Wexford Interchange project in change Franklin Park Borough and Marshall Township, Allegheny County will begin Saturday night, September 20 weather permitting.
Past Public Outreach
Public Meeting - Construction Update
Two public meeting sessions were held in September 2025. The meeting offered the opportunity for community members and interested parties to learn about anticipated traffic restrictions and future work plans directly from the project team.
Wexford Interchange Aesthetic Survey
The results are in! Thank you to everyone who participated in the I-79/Route 910 Wexford Interchange Aesthetic Survey. The winning design combination is the blue & chiseled cut ashlar stone.
Public Meeting - Design
A live virtual public meeting was held in 2023. The meeting included a presentation on the project as well as an opportunity for attendees to ask questions.
View the recording of the meeting below.
Contact Information
Zachary Kamnikar, P.E.
Project Manager
412-429-5038
zakamnikar@pa.gov
Mark Young
Environmental Planning Manager
412-429-4858
markyoung@pa.gov
Nicole Haney
Community Relations Coordinator
412-429-5011
nhaney@pa.gov
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.