Project Overview
County: Centre
State Route: US Route (Bus) 322
Local Name: South Atherton Street
Project Type: Road Construction
Proposed Start: July 2022
Proposed End: November 2024
The scope of work includes the reconstruction of South Atherton Street (State Route 3014), extending from Curtin Road to Westerly Parkway.
Construction items include roadway reconstruction, drainage improvements (including pipes and inlets), water and sewer lines, concrete curbing, sidewalks and detectable warning surfaces, pavement marking, traffic signals and supports, and other miscellaneous construction items.
Construction activities will be phased using lane restrictions and flagging. Short-term detours will be permitted for water line, sewer line, drainage and full-depth pavement reconstruction work.
-
PennDOT Announces Atherton Street Schedule for Week of May 6
-
PennDOT Announces Atherton Street Schedule for Week of April 29
-
Atherton Street Work Schedule for Week of April 22
-
PennDOT Announces Traffic Switch Coming on Atherton Street
-
PennDOT Announces Atherton Street Project Schedule for Early April
-
PennDOT Issues Update on Atherton Street Project for End of March
-
PennDOT Issues Update on Atherton Street Work for Mid-March
-
Atherton Street Project Restarting in Earnest Next Week
Contact Information
Jason Tyler
Construction Field Office Staff
814-996-4571 | 814-996-4570
jastyler@pa.gov
Marc Maney
Construction Field Office Staff
814-765-0452
mamaney@pa.gov
Timothy Nebgen
Community Relations Coordinator
814-765-0598
tnebgen@pa.gov
Eric Murnyack
Design Project Manager
814-765-0435
emurnyack@pa.gov
Project Statistics
Section: SR 3014/153
Contractor Notice to Proceed: July 11, 2022
Contract Cost: $30,702,634
Percentage Complete: 58%
Detour Information
Detour information and maps are located above.