Project Status
Step 1:
Development
Step 2:
Design
Step 3:
Construction
Step 4:
Completed
Public Outreach
Public Meeting
The SR 1022, Section 552 Culvert Replacement Project (MPMS 67565) will have a Virtual Plans Display along with a joint, in-person meeting.
A public meeting featuring a public plans display and project presentation will take place at:
Date: Thursday March 6, 2025
Time: 7:00 PM - During the Township’s regularly scheduled monthly Township Supervisors’ Meeting.
Location: Grange Hall (22130 State Route 29, Montrose, PA 18801)
Virtual Plans Display
The virtual plans display will be available on PennDOT's District 4-0 website from February 20, 2025 through March 20, 2025.
Project Overview
County: Susquehanna County
Municipality: Liberty Township
State Route: Route 1022
Project Type: Structure Replacement
Proposed Construction Start: Spring 2027
Proposed Construction End: Fall 2027
Last Updated: 02/24/2025
The Pennsylvania Department of Transportation (PennDOT) invites the public to a joint, in-person and virtual plans display regarding the Route 1022 (Liberty Park Road), Section 552 Structure Replacement Project over Tributary to Dubois Creek. The joint, in-person public meeting will take place on Thursday March 6, 2025, at the Grange Hall (22130 State Route 29, Montrose, PA 18801) at 7:00 PM during the Township’s regularly scheduled monthly Township Supervisors’ Meeting.
The purpose of this project is to address the deficiencies of the existing structure and provide continued safe and efficient crossing of the Tributary to Dubois Creek.
The Route 1022-552 project consists of replacing the existing single span metal arch culvert with a precast concrete box culvert. The reconstructed Route 1022 roadway (Liberty Park Rd) and structure will consist of two 10’-0” travel lanes with 4’-0” shoulders.
Additional work includes, but is not limited to: approach roadway reconstruction, guide rail upgrades, drainage improvements, grading, signing, and pavement markings. One utility pole relocation is also anticipated as part of the project.
Traffic will be maintained through a detour during construction. The proposed 11.3-mile detour will utilize all state routes.
The project is currently in the preliminary design phase. It is anticipated that construction will begin in the spring of 2027 and will be complete by the fall of 2027.
Detour Route and Directions
The roadway at the bridge site will be closed to all traffic and detoured during construction. The detour is expected to be in place for approximately three months.
Beginning west of the project, the vehicle detour will follow PA-29 north until reaching NY-7 (Montrose Drive). Travelers will turn right from NY-7 onto NY-7A (Conklin Road) and then continue on PA Route 1033 (New York Ave) until the intersection with Route 1037 (Dubois Street). Travelers will then connect back into Route 1022 (Liberty Park Road) for a total detour length of 11.3 miles.
Contact Information
Amy Lolli
PennDOT Project Manager
(570) 614-2958
amlolli@pa.gov
SAI Consulting Engineers
Project Designer
Two Lemoyne Drive, Suite 101
Lemoyne, PA 17043
Accessibility
The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the PennDOT Project Manager listed above.
Title VI
Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.